Project 7 - English
see attachment
RACI Matrix example
Responsible
Accountable
Consulted
Informed
Project Tasks Product Manager UI Designer Content Writer Financial Analyst Design Director VP of Product VP of Design CTO CEO
Initiation Phase
Financial Study R A I I C
Feasability Study R A I I I
Planning Phase
Technology Recommendations R C A I
Financial Plan R A I I I
Sprint Plan R A
Execution Phase
Design UI R A I C I I
Write Content R A
Create Mockup R C I A I I I
Control Phase
User Testing R A I I I
Close Phase
Create Lessons Learned R A
Create Closure Report R A I I I
How to Use the RACI Matrix Temp
How to Use the RACI Matrix Template
The RACI matrix template is tool to help everyone in the project know what their role is, so they can work better together.
Step 1: List the Project Tasks
In column 1, beneath the “Project Tasks” header, you will list all of the tasks that will be completed as part of this project. In our example, we broke the tasks down into the different project phases in order to keep things more organized. If you wish, you can remove the project phases and instead just do a large list of tasks, but we’ve found the project phases to be helpful.
Step 2: List All of Your Team Members
Next, locate the light blue bar. Going from left to right, we are going to add all of your team members to this section. Include every person in your organization, even if they won’t be working directly on the project, because stakeholders are an important part of this document too. We find it helpful to use the job title / role in this section, but you could also use team member names instead. We tend to use job titles so that this document is useful to someone looking at the matrix who may not be familiar with everybody’s name.
Step 3: Assign R,A,C,I to Each Task
Locate your first task of the project (this should be whichever task you have listed highest in Column A.) Once you’ve located your first task, move across the matrix to the right, deciding who will be (R) Responsible for executing the work on this particular task. Remember, R is for the person who will actually be performing the work on this task.
Continue moving to the right, and next you will choose who will be (A) Accountable for this task. The person who you label as (A) Accountable is the person who will be responsible for ensuring that the task is done properly and in a timely manner.
Next, you will decide who will be (C) Consulted on this task. Remember, (C) means that a person will be asked for help or advice on a task, and they will work with the responsible team member to complete the task. In some cases, you will not have a C for a task and that’s OK.
Finally, for each task you will decide who is the stakeholder for the task. The stakeholder will be labeled as (I) Informed. If someone is labeled (I) for this task, they will be updated about the progress of the task, but they will not have direct feedback going back to the person responsible for the task. An informed person is a one way communication, as compared to a consulted person who has two-way communication about the task. Most tasks will have an informed person, however there will be some cases where there is no I needed.
Step 4: Share the Document
Once your RACI chart is fully filled out, it is important to share the document with all of the team members on this project. This is an important step because a RACI matrix is most helpful when each team member understands exactly what their role is at each step of the project.
RACI Matrix Template
Responsible
Accountable
Consulted
Informed
Project Activities
Outcome 1
Outcome 2
Outcome 3
Developing a Risk Response Plan 283
Project Case Study: New Kitchen Heaven Retail Store
Ricardo knocks on your office door and asks whether you have a few minutes to talk. “Of
course,” you reply, and he takes a seat on one of the comfy chairs at the conference table.
You have a feeling this might take a while.
“I think you should know that I’m concerned about the availability of the T1 line. I’ve
already put in the call to get us on the list because, as I said last week, there’s a 30‐ to 45‐
day lead time on these orders.”
“We’re only partway through the Planning processes. Do you need to order the T1 so
soon? We don’t even know the store location yet,” you say.
“Even though they say lead time is 30 to 45 days, I’ve waited as long as five or six months
to get a T1 installed in the past. I know we’re really pushing for the early February store
opening, so I thought I’d get the ball rolling now. What I need from you is the location
address, and I’ll need that pretty quick.”
“We’re narrowing down the choices between a couple of properties, so I should have that
for you within the next couple of weeks. Is that soon enough?”
“The sooner, the better,” Ricardo replies.
“Great. I’m glad you stopped by, Ricardo. I wanted to talk with you about risk anyway, and
you led us right into the discussion. Let me ask you, what probability would you assign to
the T1 line installation happening six months from now?”
“I’d say the probability for six months is low. It’s more likely that if there is a delay, it
would be within a three‐ to four‐month time frame.”
“If they didn’t get to it for six months, would it be a showstopper? In other words, is there
some other way we could transfer Jill’s data until the T1 did get installed?”
“Sure, we could use other methods. Jill won’t want to do that for very long, but
workarounds are available.”
“Good. Now, what about the risk for contractor availability and hardware availability and
delivery schedules?” you ask.
You and Ricardo go on to discuss the risks associated with the IT tasks. Later, you ask
Jill and Jake the same kinds of questions and compile a list of risks. In addition, you
review the project information for the Atlanta store opening because it’s similar in size
Heldman, Kim. PMP: Project Management Professional Exam Study Guide : Updated for the 2015 Exam, John Wiley & Sons, Incorporated, 2015. ProQuest
Ebook Central, http://ebookcentral.proquest.com/lib/gcu/detail.action?docID=4185201.
Created from gcu on 2021-10-07 20:15:32.
C
o
p
yr
ig
h
t
©
2
0
1
5
.
Jo
h
n
W
ile
y
&
S
o
n
s,
I
n
co
rp
o
ra
te
d
.
A
ll
ri
g
h
ts
r
e
se
rv
e
d
.
284 Chapter 6 ■ Risk Planning
and scope to this store. You add the risks from that store opening to your list as well. You
divide some of the risks into the following categories: IT, Facilities, and Retail. A sample
portion of your list appears as follows, with overall assignments made based on Perform
Qualitative Risk Analysis and the probability and impact matrix:
■ Category: IT
■ T1 line availability and installation. Risk score: Low
■ Contractor availability for Ethernet installation. Risk score: Medium
■ POS and server hardware availability. Risk score: Medium
■ Category: Facilities
■ Desirable location in the right price range. Risk score: High
■ Contractor availability for build‐out. Risk score: Low
■ Availability of fixtures and shelving. Risk score: Low
■ Category: Retail
■ Product availability. Risk score: Medium
■ Shipment dates for product. Risk score: Medium
After examining the risks, you decide that response plans should be developed for the
last two items listed under the IT source, the first item under Facilities, and both of the
risks listed under Retail.
Ricardo has already mitigated the T1 connection and installation risk by signing up
several months ahead of the date when the installation is needed. The contractor
availability can be handled with a contingency plan that specifies a backup contractor
should the first choice not be available. For the POS terminals and hardware, you decide
to use the transfer strategy. As part of the contract, you’ll require these vendors to deliver
on time, and if they cannot, they’ll be required to provide and pay for rental equipment
until they can get your gear delivered.
The Facilities risk and Retail risks will be handled with a combination of acceptance,
contingency plans, and mitigation.
You’ve calculated the expected monetary value for several potential risk events. Two of
them are detailed here.
Desirable location has an expected monetary value of $780,000. The probability of
choosing an incorrect or less than desirable location is 60 percent. The potential loss in
sales is the difference between $2.5 million in sales per year that a high‐producing store
generates versus $1.2 million in sales per year that an average store generates.
Heldman, Kim. PMP: Project Management Professional Exam Study Guide : Updated for the 2015 Exam, John Wiley & Sons, Incorporated, 2015. ProQuest
Ebook Central, http://ebookcentral.proquest.com/lib/gcu/detail.action?docID=4185201.
Created from gcu on 2021-10-07 20:15:32.
C
o
p
yr
ig
h
t
©
2
0
1
5
.
Jo
h
n
W
ile
y
&
S
o
n
s,
I
n
co
rp
o
ra
te
d
.
A
ll
ri
g
h
ts
r
e
se
rv
e
d
.
Understanding How This Applies to Your Next Project 285
The expected monetary value of the product availability event is $50,000. The probability
of the event occurring is 40 percent. The potential loss in sales is $125,000 for not
opening the store in conjunction with the Home and Garden Show.
Project Case Study Checklist
■ Plan Risk Management
■ Identify Risks
■ Documentation reviews
■ Information‐gathering techniques
■ Perform Qualitative Risk Analysis
■ Risk probability and impact
■ Probability and impact rating
■ List of prioritized risks
■ Perform Quantitative Risk Analysis
■ Interviewing
■ Expected monetary value
■ Plan Risk Responses
■ Avoidance, transference, mitigation, and acceptance strategies
■ Risk response plans documented
Understanding How This Applies to
Your Next Project
Risk management, and all the processes it involves, is not a process I recommend you skip
on a project of any size. This is where the Boy Scouts of America motto, “Be Prepared,”
is wise advice. If you haven’t examined what could be lurking around the corner on your
project and come up with a plan to deal with it, then you can be assured you’re in for some
surprises. Then again, if you like living on the edge, never knowing what might occur next,
you’ll probably find yourself back on the job‐hunting scene sooner than you planned (oh,
wait, you didn’t plan because you’re living on the edge).
In all seriousness, as with most of the Planning processes I’ve discussed so far, risk
management should be scaled to match the complexity and size of your project. If you’re
working on a small project with a handful of team members and a short timeline, it doesn’t
make sense to spend a lot of time on risk planning. However, it does warrant spending
Heldman, Kim. PMP: Project Management Professional Exam Study Guide : Updated for the 2015 Exam, John Wiley & Sons, Incorporated, 2015. ProQuest
Ebook Central, http://ebookcentral.proquest.com/lib/gcu/detail.action?docID=4185201.
Created from gcu on 2021-10-07 20:15:32.
C
o
p
yr
ig
h
t
©
2
0
1
5
.
Jo
h
n
W
ile
y
&
S
o
n
s,
I
n
co
rp
o
ra
te
d
.
A
ll
ri
g
h
ts
r
e
se
rv
e
d
.
286 Chapter 6 ■ Risk Planning
some time identifying project risk, determining impact and probability, and documenting a
plan to deal with the risk.
My favorite Identify Risks technique is brainstorming. I like its cousin the Nominal
Group technique too. Both techniques help you quickly get to the risks with the greatest
probability and impact because, more than likely, these are the first risks that come to
mind. Identify Risks can also help the project team find alternative ways of completing
the work of the project. Further digging and the ideas generated from initial identification
might reveal opportunities or alternatives you wouldn’t have thought about during the
regular Planning processes.
After you’ve identified the risks with the greatest impact to the project, document
response plans that are appropriate for the risk. Small projects might have only one or
two risks that need a response plan. The plans might consist of only a sentence or two,
depending on the size of the project. I would question a project where no risks require a
response plan. If it seems too good to be true, it probably is.
The avoid, transfer, and mitigate strategies are the most often used strategies to deal
with risk, along with contingency planning. Of these, mitigation and contingency planning
are probably the most common. Mitigation generally recognizes that the risk will likely
occur and attempts to reduce the impact.
I have used brainstorming and the Nominal Group technique to strategize response
plans for risks on small projects. When you’re working on a small project, you can typically
identify, quantify, and create response plans for risks at one meeting.
Identifying positive risk, in my experience, is fairly rare. Typically, when my teams
perform Identify Risks, it’s to determine what can go wrong and how bad the impact will
be if it does. The most important concept from this chapter that you should apply to your
next project is that you and your team should identify risks and create response plans to
deal with the most significant ones.
Summary
Congratulations! You’ve completed another fun‐filled, action‐packed chapter, and all of it
on a single topic—risk. Risk is inherent in all projects, and risks pose both threats to and
opportunities for the project. Understanding the risks facing the project better equips you
to determine the appropriate strategies to deal with those risks and helps you develop the
response plans for the risks (and the level of effort you should put into preparing those
plans).
The Plan Risk Management process determines how you will plan for risks on your
project. Its only output is the risk management plan, which details how you’ll define,
monitor, and control risks throughout the project. The risk management plan is a
subsidiary of the project management plan.
The Identify Risks process seeks to identify and document the project risks using
information‐gathering techniques such as brainstorming, the Delphi technique,
Heldman, Kim. PMP: Project Management Professional Exam Study Guide : Updated for the 2015 Exam, John Wiley & Sons, Incorporated, 2015. ProQuest
Ebook Central, http://ebookcentral.proquest.com/lib/gcu/detail.action?docID=4185201.
Created from gcu on 2021-10-07 20:15:32.
C
o
p
yr
ig
h
t
©
2
0
1
5
.
Jo
h
n
W
ile
y
&
S
o
n
s,
I
n
co
rp
o
ra
te
d
.
A
ll
ri
g
h
ts
r
e
se
rv
e
d
.
Exam Essentials 287
interviewing, and root cause analysis. This list of risks gets recorded in the risk register, the
only output of this process.
Perform Qualitative Risk Analysis and Perform Quantitative Risk Analysis involve
evaluating risks and assigning probability and impact values to them. Many tools
and techniques are used during these processes, including risk probability and impact
assessment, probability and impact matrix, interviewing, probability distributions, expert
judgment, sensitivity analysis, decision tree analysis, and simulation.
A probability and impact matrix uses the probability multiplied by the impact value to
determine the risk score. The threshold of risk based on high, medium, and low tolerances
is determined by comparing the risk score based on the probability level to the probability
and impact matrix.
Monte Carlo simulation is a technique used to quantify schedule or cost risks. Decision
trees graphically display decisions and their various choices and outcomes, and they are
typically used in combination with expected monetary value.
The Plan Risk Responses process is the last Planning process and culminates with an
update to the risk register documenting the risk response plans. The risk response plans
detail the strategies you’ll use to respond to risk and assign individuals to manage each
risk response. Risk response strategies for negative risks include avoidance, mitigation,
and transference. Risk strategies for positive risks include exploit, share, and enhance.
Acceptance is a strategy for both negative and positive risks.
Contingency planning involves planning alternatives to deal with risk events should they
occur. Contingency reserves are set aside to deal with risks associated with cost and time
according to the stakeholder tolerance levels.
Exam Essentials
Be able to define the purpose of the risk management plan. The risk management plan
describes how you will define, monitor, and control risks throughout the project. It details
how risk management processes (including Identify Risks, Perform Qualitative Risk
Analysis, Perform Quantitative Risk Analysis, Plan Risk Responses, and Control Risks)
will be implemented, monitored, and controlled throughout the life of the project. It
describes how you will manage risks but does not attempt to define responses to individual
risks. The risk management plan is a subsidiary of the project management plan, and it’s
the only output of the Plan Risk Management process.
Be able to name the purpose of Identify Risks. The purpose of the Identify Risks process
is to identify all risks that might impact the project and then document them and identify
their characteristics.
Be able to define the purpose of Perform Qualitative Risk Analysis. Perform Qualitative
Risk Analysis determines the impact the identified risks will have on the project and the
Heldman, Kim. PMP: Project Management Professional Exam Study Guide : Updated for the 2015 Exam, John Wiley & Sons, Incorporated, 2015. ProQuest
Ebook Central, http://ebookcentral.proquest.com/lib/gcu/detail.action?docID=4185201.
Created from gcu on 2021-10-07 20:15:32.
C
o
p
yr
ig
h
t
©
2
0
1
5
.
Jo
h
n
W
ile
y
&
S
o
n
s,
I
n
co
rp
o
ra
te
d
.
A
ll
ri
g
h
ts
r
e
se
rv
e
d
.
Introducing the Kitchen Heaven Project Case Study 83
Once the stakeholder assessment is complete, you should devise a plan to deal with any
potential impacts and/or potential strategies for gaining their support.
Remember that the definition of a successful project is one that
accomplishes the goals of the project and meets stakeholders’ expectations.
Understand and document those expectations and you’re off to a good
start.
Stakeholder Register and Strategy
Stakeholder register is the only output of this process. The stakeholder register contains the
information we discussed earlier about the stakeholder register template. In addition to the
elements we already discussed, the stakeholder register should contain at least the following
details, according to the PMBOK® Guide:
Identifying Information This includes items such as contact information, department, role
in the project, and so on.
Assessment Information This includes elements regarding influence, expectations, key
requirements, and when the stakeholder involvement is most critical.
Stakeholder Classification Stakeholders can be classified according to their relationship
to the organization (internal or external, for example) and, more important, whether they
support the project, are resistant to the project, or have no opinion.
Remember that project documents are usually easily accessible by the
project team and stakeholders. Use caution when documenting sensitive
information regarding a stakeholder and your strategy for dealing with that
stakeholder because it could become public knowledge.
Introducing the Kitchen Heaven
Project Case Study
This chapter introduces a case study that we’ll follow throughout the remainder of the
book. The case study is updated at the end of every chapter. It’s designed to show you how
a project manager might apply the material covered in the chapter to a real‐life project.
As happens in real life, not every detail of every process is followed during all projects.
Remember that the processes from the PMBOK® Guide that I’ll cover in the remaining
chapters are project management guidelines. You will often combine processes during your
projects, which will allow you to perform several steps at once. The case study will present
Heldman, Kim. PMP: Project Management Professional Exam Study Guide : Updated for the 2015 Exam, John Wiley & Sons, Incorporated, 2015. ProQuest
Ebook Central, http://ebookcentral.proquest.com/lib/gcu/detail.action?docID=4185201.
Created from gcu on 2021-09-15 18:11:07.
C
o
p
yr
ig
h
t
©
2
0
1
5
.
Jo
h
n
W
ile
y
&
S
o
n
s,
I
n
co
rp
o
ra
te
d
.
A
ll
ri
g
h
ts
r
e
se
rv
e
d
.
84 Chapter 2 ■ Creating the Project Charter
situations or processes that you might find during your projects and describe how one
project manager resolves them.
Project Case study: new kitchen heaven retail store
You are a project manager for Kitchen Heaven, a chain of retail stores specializing in
kitchen utensils, cookware, dishes, small appliances, and some gourmet foodstuffs,
such as bottled sauces and spices. You’re fairly new to the position, having been hired to
replace a project manager who recently retired.
Kitchen Heaven currently owns 49 stores in 34 states and Canada. The world
headquarters for Kitchen Heaven is in Denver, Colorado. Counting full‐time and part‐time
employees, the company employs 1,500 people, 200 of whom work at headquarters.
The company’s mission statement reads, “Great gadgets for people interested in great food.”
Recently, the vice president of marketing paid you a visit. Dirk Perrier is a very nice,
well‐dressed man with the formal air you would expect a person in his capacity might
have. He shakes your hand and gives you a broad, friendly smile.
“We’ve decided to go forward with our 50th store opening! Sales are up, and our new line
of ceramic cookware is a hot seller, no pun intended. I don’t know if you’re familiar with
our store philosophy, so let me take a moment to explain it. We like to place our stores in
neighborhoods that are somewhat affluent. The plain fact is that most of our shoppers
have incomes of more than $150,000 a year. So, we make an effort to place our stores in
areas where those folks usually shop.
“We’re targeting the type of customer who watches the Food Network channel and must
have all the gadgets and tools they see the famous chefs using. So, the stores are upbeat
and convey a fun, energetic feel, if you will.
“Our next store is going to be right here in our home area—Colorado Springs. Because
this is going to be our 50th store, we plan on having a 50th grand‐opening celebration,
with the kind of surprises and activities you might expect for such a notable opening.
“Our stores generally occupy from 1,500 to 2,500 square feet of retail space, and we
typically use local contractors for the build‐out. A store build‐out usually takes 120 days
from the date the property has been procured until the doors open to the public. I can
give you our last opening’s project plan so you have a feel for what happens. Your job
will be to procure the property, negotiate the lease, procure the shelving and associated
store furnishings, get a contractor on the job, and prepare the 50th store festivities. My
marketing folks will assist you with that last part.
“You have six months to complete the project. Any questions?”
Heldman, Kim. PMP: Project Management Professional Exam Study Guide : Updated for the 2015 Exam, John Wiley & Sons, Incorporated, 2015. ProQuest
Ebook Central, http://ebookcentral.proquest.com/lib/gcu/detail.action?docID=4185201.
Created from gcu on 2021-09-15 18:11:07.
C
o
p
yr
ig
h
t
©
2
0
1
5
.
Jo
h
n
W
ile
y
&
S
o
n
s,
I
n
co
rp
o
ra
te
d
.
A
ll
ri
g
h
ts
r
e
se
rv
e
d
.
Introducing the Kitchen Heaven Project Case Study 85
You take in a deep breath and collect your thoughts. Dirk has just given you a lot of
information with hardly a pause between thoughts. A few initial ideas drift through your
head while you’re reaching for your notebook.
You work in a functional organization with a separate projectized department responsible
for carrying out projects of this nature. You’ve been with the company long enough to
know that Dirk is high up there in the executive ranks and carries the authority and power
to make things happen. Therefore, Dirk is the perfect candidate for project sponsor.
You grab your notebook and start documenting some of the things Dirk talked about,
clarifying with him as you write:
The project objective is to open a new store in Colorado Springs six months from today.
The store should be located in an affluent area.
The store will carry the full line of products, from utensils to gourmet food items.
The grand opening will be accompanied by lots of fanfare because this is the 50th store
opening.
You have a question or two for Dirk.
“Is there a special reason we have to open, let’s see, six months from now, which is
February 1?”
He responds, “Yes, we want the store open the first week in February. Early February is
when the Garden and Home Show conference hits the Springs area. We’ll have a trade
show booth there. We know from experience in other areas that our stores generally see
a surge in sales during this month as a result of the trade show. It’s a great way to get a
lot of advertising out there and let folks know where we’re located.”
“Another question, Dirk. Is there a budget set for this project yet?”
“We haven’t set a hard figure,” Dirk replies. “But again, from past experience we know it
takes anywhere from $1.5 to $2 million to open a new store—and we don’t want to forget
the big bash for the grand opening.”
“Thanks, Dirk. I’ll get started writing the project charter right away. I’ll put your name on
the document because you’re the project sponsor.”
Dirk concludes with, “Feel free to come to me with questions or concerns at any time.”
One week later.
You review your notes and reread the project charter you’ve prepared for the Kitchen
Heaven retail store one last time before looking for Dirk. You finally run across Dirk in a
hallway near the executive washroom.
Heldman, Kim. PMP: Project Management Professional Exam Study Guide : Updated for the 2015 Exam, John Wiley & Sons, Incorporated, 2015. ProQuest
Ebook Central, http://ebookcentral.proquest.com/lib/gcu/detail.action?docID=4185201.
Created from gcu on 2021-09-15 18:11:07.
C
o
p
yr
ig
h
t
©
2
0
1
5
.
Jo
h
n
W
ile
y
&
S
o
n
s,
I
n
co
rp
o
ra
te
d
.
A
ll
ri
g
h
ts
r
e
se
rv
e
d
.
86 Chapter 2 ■ Creating the Project Charter
“Dirk, I’m glad I caught you. I’d like to go over the project charter with you before the
kickoff meeting tomorrow. Do you have a few minutes?”
“Sure,” Dirk says to you. “Let’s have it.”
“The project charter states the purpose of the project, which of course is to open the
50th Kitchen Heaven store in Colorado Springs. I also documented some of the high‐
level requirements, many of which we talked about last time we met. I documented
the assumptions and constraints you gave me with the understanding that we’ll define
these much more closely when I create the scope statement. I’ve included a section
that outlines a preliminary milestone schedule, and I’ve included some preliminary ROI
[return on investment] calculations. Using your estimate of $2 million as our initial budget
request and based on the projected inflows you gave me last week, I’ve calculated a
payback period of 19 months, with an IRR [internal rate of return] of 6 percent.”
“That’s impressive,” replies Dirk. “That’s even better than our Phoenix store. If I recall,
the payback period there was just over two years. Let’s hope those numbers hold true.”
“I think they’re reliable figures,” you say. “I researched our data based on recent store
openings in similar‐sized cities and factored in the economic conditions of the Colorado
Springs area. Since they’re on a growth pattern, we think the timing is perfect.
“As you know, the project kickoff is scheduled for tomorrow. What I’ll need, then, is for
you to talk about the project and the goals, talk about the commitment you’ll need from
the management team to support this project, and introduce me as the project manager.
I’ve already forwarded a copy of the project charter to the meeting attendees so that they
can review it before the meeting. I included a list of the assumptions we’ve made so far
as an appendix to the charter. Last, I’ll need you to ask everyone present to sign a copy of
the project charter.”
“Sounds like you’ve covered everything,” Dirk says. “I don’t anticipate any problems
tomorrow, because everyone is looking forward to this store opening.”
Project Case Study Checklist
■ Project objective: To open a new store in Colorado Springs six months from today.
■ Business need or demand for project: Company data concludes that the Kitchen
Heaven consumers have incomes of more than $150,000 a year. The Colorado
Springs area is home to a large number of people with that income. Currently, there
is no Kitchen Heaven in the area, but there appears to be a demand for one.
■ Project sponsor: Dirk Perrier, VP of marketing.
■ Organizational structure: Functional organization with a separate projectized
department.
■ Project selection methods: Payback period calculated at 19 months and IRR
calculated at 6 percent.
Heldman, Kim. PMP: Project Management Professional Exam Study Guide : Updated for the 2015 Exam, John Wiley & Sons, Incorporated, 2015. ProQuest
Ebook Central, http://ebookcentral.proquest.com/lib/gcu/detail.action?docID=4185201.
Created from gcu on 2021-09-15 18:11:07.
C
o
p
yr
ig
h
t
©
2
0
1
5
.
Jo
h
n
W
ile
y
&
S
o
n
s,
I
n
co
rp
o
ra
te
d
.
A
ll
ri
g
h
ts
r
e
se
rv
e
d
.
Understanding How This Applies to Your Next Project 87
■ Created project charter: Project charter contains the following:
■ High‐level overview of project
■ List of measurable project objectives
■ High‐level risks
■ Summary milestone schedule with initial completion date of February 1
■ Summary budget of $2 million
■ Project manager authority levels
■ Definition of roles of project sponsor and project manager
■ Next steps: Kickoff meeting set up to discuss charter and obtain sign‐off.
Understanding How This Applies to
Your Next Project
There are as many ways to select and prioritize projects as there are organizations. You
might be profit driven, so money will be king. You might have a stakeholder committee
that weighs the pros and cons, or you might have an executive director who determines
which project is up next. Scoring models and cash flow analysis techniques are useful on
the job. Whether your organization uses these methods or others, an organized, consistent
way to select and prioritize projects is necessary. I know I could work the next 100 years
straight and probably still not get all the projects completed my organization would like to
see implemented. What I’ve found is that the selection method must be fair and reasonable.
If your organization uses an arbitrary method—say you like Tara better than Joe, so Tara’s
projects always end up on the “yes” list—it won’t be long before stakeholders demand
that another method be devised to select projects that everyone can understand. Whatever
method you’re using, stick to it consistently.
If you’re like me, when I’m faced with a new project I want to get right to the heart
of the matter and understand the purpose of the project. Projects come about for many
reasons. Most of the time, understanding the reason it came about will give you some
insight into its purpose. For example, if a new law is passed that requires anyone applying
for a driver’s license to show two forms of identification but the existing system has the
space to record verification of only one document, you immediately have a firm grasp on
the purpose of the project—you’ll have to update the system to include additional space for
recording the second document.
It has been my experience in working with project teams that when the team
understands the reason or the need that brought about the project and it understands the
goal of the project, the project is more successful. I don’t have any scientific evidence for
Heldman, Kim. PMP: Project Management Professional Exam Study Guide : Updated for the 2015 Exam, John Wiley & Sons, Incorporated, 2015. ProQuest
Ebook Central, http://ebookcentral.proquest.com/lib/gcu/detail.action?docID=4185201.
Created from gcu on 2021-09-15 18:11:07.
C
o
p
yr
ig
h
t
©
2
0
1
5
.
Jo
h
n
W
ile
y
&
S
o
n
s,
I
n
co
rp
o
ra
te
d
.
A
ll
ri
g
h
ts
r
e
se
rv
e
d
.
190 Chapter 4 ■ Creating the Project Schedule
In practice, for small to medium‐sized projects, you can complete Define Activities,
Sequence Activities, Estimate Activity Resources, Estimate Activity Durations, and Develop
Schedule at the same time with the aid of a project management software tool. You can
produce Gantt charts; you can produce the critical path, resource allocation, and activity
dependencies; you can perform what‐if analysis; and you can produce various reports
after plugging your scheduling information into most project management software tools.
Regardless of your methods, be certain to obtain sign‐off on the project schedule and
provide your stakeholders and project sponsor with regular updates. Keep your schedule
handy—there will likely be changes and modifications as you go. While you’re at it,
be certain to save a schedule baseline for comparative purposes. Once you get into the
Executing and Monitoring and Controlling processes, you’ll be able to compare what you
planned to do against what actually happened.
schedule data
The schedule data refers to documenting the supporting data for the schedule. The
minimum amount of information in this output includes the milestones, schedule activities
and activity attributes, and the assumptions and constraints regarding the schedule.
You should document any other information that doesn’t necessarily fit into the other
categories. Always err on the side of too much documentation rather than not enough.
You will have to be the judge of what other information to include here because it
will depend on the nature of the project. The PMBOK® Guide suggests that you might
include schedule contingencies, alternative schedules, and resource histograms. Chapter 7,
“Planning Project Resources,” contains an example of a resource histogram if you want to
peek ahead. Resource histograms typically display hours needed on one axis and period
of time (days, weeks, months, years) on the other axis. You might also include alternative
schedules or contingency schedule reserves in the schedule data section.
Project documents updates
As with many of the other processes you’ve seen in this chapter, creating the project
schedule may require updates to the activity resource requirements document, activity
attributes, calendars, and the risk register.
Project Case Study: New Kitchen Heaven retail Store
You worked with the stakeholders to document the activity list last week. After creating
the first draft of the project schedule network diagram, you went back to each of them to
ask for time estimates for each of the activities. Ricardo’s estimates are shown here:
1. Procure the T1 connection. This takes 30 to 45 days. This activity can be done
concurrently with the other activities listed here. Ricardo will perform this activity.
Heldman, Kim. PMP: Project Management Professional Exam Study Guide : Updated for the 2015 Exam, John Wiley & Sons, Incorporated, 2015. ProQuest
Ebook Central, http://ebookcentral.proquest.com/lib/gcu/detail.action?docID=4185201.
Created from gcu on 2021-10-07 20:15:55.
C
o
p
yr
ig
h
t
©
2
0
1
5
.
Jo
h
n
W
ile
y
&
S
o
n
s,
I
n
co
rp
o
ra
te
d
.
A
ll
ri
g
h
ts
r
e
se
rv
e
d
.
Developing the Project Schedule 191
2. Run Ethernet cable throughout the building. This activity depends on the lease
being signed and must finish before the build‐out can start. The estimated time to
complete is 16 hours, which was figured using parametric estimating techniques.
Ricardo has one person on staff who can complete this specialized activity. His first
available date is October 5.
3. Purchase the router, switch, server, and rack for the equipment room and the four
point‐of‐service terminals. Delivery time is two weeks. Ricardo will perform this
activity.
4. Install the router and test the connection. Testing depends on the T1 installation at
demarcation. The time estimate to install is eight hours. Ricardo’s staff will perform
this activity.
5. Install the switch. Based on past experience, the time estimate to install is two hours.
Ricardo’s staff will do this activity.
6. Install the server and test. The testing depends on the T1 connection installation.
Based on past experience, the time estimate to install is six hours. Ricardo’s staff will
do this activity.
7. The web team will add the new store location and phone number to the lookup
function on the Internet site. The time estimate is two hours. Ricardo will assign his
applications programming manager to this activity. This activity depends on the
lease being signed.
Jake and Jill have each written similar lists with estimates and potential resource
assignments. You begin to align all the activities in sequential order and discover a
problem. Jill needs 14 days to hire personnel and stock shelves, meaning that the build‐
out must be finished by January 16. Build‐out takes approximately 120 days and can’t start
before September 20 because of the contractor’s availability. This is a problem because
Ricardo’s Ethernet cable expert isn’t available until October 5, and he needs 2 days to
complete the cabling. This pushes out the build‐out start date by almost 2 weeks, which
means the project completion date, or store‐opening date, is delayed by 2 weeks.
After gathering more information from Ricardo, you head to Dirk’s office.
“So, Dirk,” you conclude after filling him in on all the details, “we have two options. Hire
a contractor to perform the cable run since Ricardo’s person isn’t available or push the
store opening out by two weeks.”
Dirk asks, “How much will the contractor charge to run the cable, and are they available
within the time frame you need?”
“Yes, they are available, and I’ve already requested that Ricardo book the week of
September 18 to hold this option open for us. They’ve quoted a price of $10,000.”
“Okay, let’s bring in the contractor. At this point, $10,000 isn’t going to break the budget.
How is that planning coming anyway? Signed a lease yet?”
Heldman, Kim. PMP: Project Management Professional Exam Study Guide : Updated for the 2015 Exam, John Wiley & Sons, Incorporated, 2015. ProQuest
Ebook Central, http://ebookcentral.proquest.com/lib/gcu/detail.action?docID=4185201.
Created from gcu on 2021-10-07 20:15:55.
C
o
p
yr
ig
h
t
©
2
0
1
5
.
Jo
h
n
W
ile
y
&
S
o
n
s,
I
n
co
rp
o
ra
te
d
.
A
ll
ri
g
h
ts
r
e
se
rv
e
d
.
192 Chapter 4 ■ Creating the Project Schedule
“Yes, we’ve signed the lease. Jake has been meeting with Gomez Construction on the
build‐out. We’ve used Gomez on three out of the last five new stores and have had good
luck with them.”
You spend the next couple of days working on the project schedule in Microsoft Project,
clarifying tasks and activities with Jake, Ricardo, and Jill. You decide that a Gantt chart
will work excellently for reporting status for this project. You stare intensely at the
problem you see on the screen. The Grand Opening task is scheduled to occur 13 days
later than when you need it! The grand opening must happen February 1 and 2, not
February 14 and 15 as the schedule shows. You trace the problem back and see that the
Grand Opening task depends on Train Store Personnel, which itself depends on several
other tasks, including Hire Store Personnel and Install and Test Hardware. Digging
deeper, build‐out can’t begin until the Ethernet cable is run throughout the building.
Ricardo already set up the time with the contractor to run the cable on September 18.
This date cannot move, which means build‐out cannot start any sooner than September
20, which works with Gomez’s availability.
You pick up the phone and dial Jake’s number. “Jake,” you say into the receiver, “I’m
working on the project schedule, and I have some issues with the Gomez activity.”
“Shoot,” Jake says.
“Gomez Construction can’t start work until the Ethernet cable is run. I’ve already
confirmed with Ricardo that there is no negotiation on this. Ricardo is hiring a contractor
for this activity, and the earliest they can start is September 18. It takes them two days to
run the cable, which puts the start date for build‐out at September 20.”
“What’s the problem with the September 20 date?” Jake asks
“Jill wants to have the build‐out finished prior to hiring the store personnel. During the
last store opening, those activities overlapped, and she said it was unmanageable. She
wants to hire folks and have them stock the shelves in preparation for store opening but
doesn’t want contractors in there while they’re doing it. A September 20 start date for
Gomez puts us at a finish date of January 26, which is too late to give Jill time to hire and
stock shelves. My question is this: Is 120 days to finish a build‐out a firm estimate?”
“Always—I’ve got this down to a science. Gomez has worked with me on enough of these
build‐outs that we can come within just a couple of days of this estimate either way,” Jake says.
You pick up your schedule detail and continue, “I’ve scheduled Gomez’s resource
calendar as you told me originally. Gomez doesn’t work Sundays, and neither do we.
Their holidays are Labor Day, a couple of days at Thanksgiving, Christmas, and New
Year’s, but this puts us too far out on the schedule. Our February 1 opening must coincide
with the Home and Garden Show dates.”
“I can’t change the 120 days. Sounds like you have a problem.”
“I need to crash the schedule,” you say. “What would the chances be of Gomez agreeing
to split the build‐out tasks? We could hire a second contractor to come in and work
Heldman, Kim. PMP: Project Management Professional Exam Study Guide : Updated for the 2015 Exam, John Wiley & Sons, Incorporated, 2015. ProQuest
Ebook Central, http://ebookcentral.proquest.com/lib/gcu/detail.action?docID=4185201.
Created from gcu on 2021-10-07 20:15:55.
C
o
p
yr
ig
h
t
©
2
0
1
5
.
Jo
h
n
W
ile
y
&
S
o
n
s,
I
n
co
rp
o
ra
te
d
.
A
ll
ri
g
h
ts
r
e
se
rv
e
d
.
Developing the Project Schedule 193
alongside Gomez’s crew to speed up this task. That would shorten the duration to 100
days, which means we could meet the February 1 date.”
“Won’t happen. I know Gomez. They’re a big outfit and have all their own crews. We
typically work with them exclusively. If I brought another contractor into the picture, I
might have a hard time negotiating any kind of favors with them later if we get into a
bind.”
“All right,” you say. “How about this? I’m making some changes to the resource calendar
while we’re talking. What if we authorize Gomez’s crew to work six 10‐hour days, which
still leaves them with Sundays off, and we ask them to work on Labor Day and take only
one day at Thanksgiving instead of two?”
“I think Gomez would go for that. You realize it’s going to cost you?”
“Project management is all about trade‐offs. We can’t move the start date, so chances are
the budget might take a hit to accommodate schedule changes or risk. Fortunately, I’m
just now wrapping up the final funding requirements, so if you can get me the increased
cost from Gomez soon, I’d appreciate it. This change will keep us on track and resolve
Jill’s issues too.”
“I don’t think Gomez’s crew will mind the overtime during the holiday season. Everyone
can use a little extra cash at that time of year, it seems. I’ll have the figures for you in a
day or two.”
Project Case Study Checklist
The main topics discussed in the case study are as follows:
Estimate Activity Durations
Estimate Activity Resources
Developing project schedule
Calendars
Lead and lag time
Critical path
Duration compression
Crashing
Fast tracking
Utilizing project management software
Producing project schedule
Milestones
Gantt chart
Resource leveling
Heldman, Kim. PMP: Project Management Professional Exam Study Guide : Updated for the 2015 Exam, John Wiley & Sons, Incorporated, 2015. ProQuest
Ebook Central, http://ebookcentral.proquest.com/lib/gcu/detail.action?docID=4185201.
Created from gcu on 2021-10-07 20:15:55.
C
o
p
yr
ig
h
t
©
2
0
1
5
.
Jo
h
n
W
ile
y
&
S
o
n
s,
I
n
co
rp
o
ra
te
d
.
A
ll
ri
g
h
ts
r
e
se
rv
e
d
.
138 Chapter 3 ■ Developing the Project Scope Statement
■ Contract or agreements information
■ Constraints and assumptions
Let’s look at an example of what some of the elements of a WBS dictionary entry might
look like. You’ll use the work package level called Inspection and Identification defined in
the sidebar “The Lincoln Street Office Building” earlier. The WBS dictionary entry for this
might look like the following:
3.1 Inspection and Identification
Description of work—Inspect the building for asbestos, and identify all areas where
it’s found. Update the plan for removal (WBS 2.2) with each location identified.
Responsible organization—Adrian in facilities will hire and oversee a contractor
to perform this work.
Schedule milestones—Inspection and identification to start after contractor is
identified and hired (no later than July 1). Work should be completed no later than
September 15.
Contract information—Two contractors have been identified as qualified and
experienced in this type of work. Contract process should close no later than June 12.
If the WBS and the WBS dictionary are constructed well, you’ve given yourself a huge
helping hand with the remaining Planning processes. The completion of many of the
remaining processes depends on the project scope statement and WBS being accurate and
complete. You’ll use the work packages created here to further elaborate the work into
activities. From there, you can estimate costs, develop schedules, and so on. The WBS is an
essential tool for project planning, so keep it handy.
Project documents updates
Project documents updates might include updates to the requirements document, which
can come about as a result of changes that occur when you’re creating the WBS. You can
see from the examples you’ve walked through in this chapter how new deliverables or
requirements might surface as a result of working on the WBS. These requested changes
should be reviewed and either approved or denied using your change control processes. The
approved changes will likely change the project scope statement, the project management
plan, and other project documents. These documents should be updated to reflect the
approved changes.
I recommend reviewing Practice Standard for Work Breakdown Structures,
Second Edition, published by PMI, to see examples of industry‐specific
WBS templates, or you can modify the templates for particular business
areas that may not be represented.
Heldman, Kim. PMP: Project Management Professional Exam Study Guide : Updated for the 2015 Exam, John Wiley & Sons, Incorporated, 2015. ProQuest
Ebook Central, http://ebookcentral.proquest.com/lib/gcu/detail.action?docID=4185201.
Created from gcu on 2021-09-30 17:08:46.
C
o
p
yr
ig
h
t
©
2
0
1
5
.
Jo
h
n
W
ile
y
&
S
o
n
s,
I
n
co
rp
o
ra
te
d
.
A
ll
ri
g
h
ts
r
e
se
rv
e
d
.
Creating the Work Breakdown Structure 139
Project Case Study: New Kitchen Heaven Retail Store
The project charter kickoff meeting was held and well attended. You’re ready to start
gathering requirements and writing the project scope statement, and you have a question
or two for Dirk. You knock on his door, and he invites you in.
“Shoot,” he says.
“I’m ready to define the deliverables and requirements for this project. I want to
make sure I get the right folks involved in the meeting. Who are key stakeholders you
recommend I speak with?”
“I can think of a few people right off that you don’t want to miss. There’s Jake Peterson
over in facilities. He’s in charge of store furnishings, shelving, things like that—any
supplies for the stores that aren’t retail products. He can help out with store build‐outs
too. He supervised our last eight stores and did a terrific job.”
“Anyone else?” you ask.
“You should also talk to Jill Overstreet, the director in charge of retail products. She can
help with the initial store stocking, and once the store is open, her group will take over the
ongoing operations. All the district managers report to Jill.”
You thank Dirk and tell him you’re going to contact Jake and Jill and set up a
brainstorming session to determine requirements.
A few days later.
You review your notes and reread the first draft of the project scope statement you’ve
prepared for the Kitchen Heaven retail store before looking for Dirk. After your meetings
with the stakeholders, you were better able to refine the project objectives and deliverables.
“Dirk, I’m glad I caught you. I’d like to go over the project scope statement with you
before I give it to the stakeholders. Do you have a few minutes?”
“Sure,” Dirk says. “Let’s have it.”
“The project objective is to open the 50th Kitchen Heaven store in Colorado Springs by
February 1. When I met with Jake, he confirmed it takes 120 days to do the store build‐
out. That includes having the shelves set up and in place, ready to stock with inventory.”
Dirk asks whether Jake told you about his store location idea.
“Yes, Jake gave me a contact name of the leasing agent, and I’ve left her a voicemail. The
sooner we can get that lease signed, the better. It takes Jake 120 days to do the build‐out,
and Jill said she needs two weeks lead time to order the initial inventory and stock the
shelves. That puts us pretty close to our February 1 deadline, counting the time to get the
lease papers signed.”
Heldman, Kim. PMP: Project Management Professional Exam Study Guide : Updated for the 2015 Exam, John Wiley & Sons, Incorporated, 2015. ProQuest
Ebook Central, http://ebookcentral.proquest.com/lib/gcu/detail.action?docID=4185201.
Created from gcu on 2021-09-30 17:08:46.
C
o
p
yr
ig
h
t
©
2
0
1
5
.
Jo
h
n
W
ile
y
&
S
o
n
s,
I
n
co
rp
o
ra
te
d
.
A
ll
ri
g
h
ts
r
e
se
rv
e
d
.
140 Chapter 3 ■ Developing the Project Scope Statement
“Sounds good so far,” Dirk replies. “What else?”
You continue, “I’ve included an updated description of the products and services the new
store will offer, based on the documentation that was written from the last store opening.
Jill reviewed the updates to the description, so we should be in the clear there. The store
will include some new lines that we’ve decided to take on—cookware from famous chefs,
that kind of thing.
“Jake has already made contact with a general contractor in Colorado Springs, and he is
ready to roll once we’ve signed the lease.
“One more thing, Dirk. Since we’re including the big bash at the grand opening as part of
the deliverables, I talked to some of your folks in marketing to get some ideas. They are
thinking we should have some great giveaways as door prizes and that we will want the
food catered. They also thought having some live cooking demonstrations with some
local chefs would be a good attraction.”
“Sounds like you’re on the right track. So, what’s next?” Dirk asks.
“Once you approve the scope statement, I’d like to send a copy to the stakeholders. My
next step is to break down the deliverables and requirements I’ve documented here into
the WBS so we can get rolling on the work of the project.”
Project Case Study Checklist
The main topics discussed in the case study are as follows:
stakeholder analysis for requirements gathering: Jake Peterson and Jill Overstreet
interviewed. Needs, wants, and expectations recorded and requirements
prioritized.
organizational structure: Functional organization with a separate projectized
department.
constraints: February 1 date to coincide with Garden and Home show.
assumptions: These are the assumptions:
■ A store build‐out usually takes 120 days.
■ Jill Overstreet will help with the initial store stocking.
■ Jake Peterson will provide supplies for the stores that aren’t retail products, such
as store furnishings, shelving, and so on, and can help with the store build‐out as
well.
■ The budget for the project will be between $1.5 and $2 million.
The project scope statement includes the following:
Project objectives: Open 50th store by February 1 in Colorado Springs.
Heldman, Kim. PMP: Project Management Professional Exam Study Guide : Updated for the 2015 Exam, John Wiley & Sons, Incorporated, 2015. ProQuest
Ebook Central, http://ebookcentral.proquest.com/lib/gcu/detail.action?docID=4185201.
Created from gcu on 2021-09-30 17:08:46.
C
o
p
yr
ig
h
t
©
2
0
1
5
.
Jo
h
n
W
ile
y
&
S
o
n
s,
I
n
co
rp
o
ra
te
d
.
A
ll
ri
g
h
ts
r
e
se
rv
e
d
.
Understanding How This Applies to Your Next Project 141
Project deliverables:
■ Build out storefront, including shelving.
■ Retail product line will be delivered two weeks prior to grand opening.
■ Have grand‐opening party with cooking demos.
Project requirements:
■ Sign lease within 14 days.
■ Offer new line of gourmet food products.
■ Have classroom space in back of store for cooking demos and classes.
constraints: February 1 date will coincide with Garden and Home Show.
fund limitations: Spend no more than $2 million on the project.
assumptions: (These are the same as listed earlier.) Decomposed deliverables into a WBS.
The WBS includes the following:
■ Level one is the project.
■ Level two is subprojects or deliverables.
■ Level three is deliverables.
■ Last level of WBS is the work package level, where time and cost estimates can be
defined in the next process.
Understanding How This Applies to
Your Next Project
In this chapter, you dealt with the realities of life on the job. The reality is, many project
managers I know are managing several projects at once as opposed to one large project.
Although every concept presented in this chapter is a sound one, it’s important to note that
you have to balance the amount of effort you’ll put into project management processes
against the size and complexity of the project.
As a manager who prides herself and her team on excellent customer service, I have once
or twice gotten my team into precarious situations because I was so focused on helping
the customer that I hurt them and our department in the process. If you’re wondering
how that happened, it was because we didn’t take the time to document the scope of
the project and the final acceptance criteria. In one case, in the interest of getting the
project completed quickly because of our customer’s own internal deadlines, we decided
the project was straightforward enough that we didn’t need to document deliverables.
Heldman, Kim. PMP: Project Management Professional Exam Study Guide : Updated for the 2015 Exam, John Wiley & Sons, Incorporated, 2015. ProQuest
Ebook Central, http://ebookcentral.proquest.com/lib/gcu/detail.action?docID=4185201.
Created from gcu on 2021-09-30 17:08:46.
C
o
p
yr
ig
h
t
©
2
0
1
5
.
Jo
h
n
W
ile
y
&
S
o
n
s,
I
n
co
rp
o
ra
te
d
.
A
ll
ri
g
h
ts
r
e
se
rv
e
d
.
142 Chapter 3 ■ Developing the Project Scope Statement
The customer promised to work side by side with us as we produced the work of the
project. Unfortunately, that wasn’t the case, and we didn’t meet the expectations of our
customer. Further, after we did implement the project (two months behind schedule), we
went through another six weeks of “fixes” because of the miscommunication between
the customer and the project team on what constituted some of the features of the final
product. There’s always a great reason for cutting corners—but they almost always come
back to haunt you. My advice is to always create a scope statement and a requirements
document and get stakeholder signatures on both. (In practice, small projects can include
both the deliverables and requirements within the scope statement.)
Decomposing the deliverables is the first step toward determining resource requirements
and estimates. A WBS is always a good idea, no matter the size of the project. I have to
admit I have cheated a time or two on small projects and used the project schedule as the
WBS. In all fairness, that worked out fine when the team was small and there weren’t more
than three or four people working on the project. If you get many more than four people
on the project team, it can be a little cumbersome to track deliverables with a schedule
only. The WBS is the perfect tool to use to assign names to work packages, and it’s the
foundation for determining estimates for the work of the project.
The five‐step process outlined by the PMBOK® Guide works very well. Starting with
the 50,000‐foot view, the team determines the major deliverables of the project. From
there, the deliverables are decomposed into ever smaller units of work. The trick here is
to break the work down into measurable units so that you can verify the status of the
work and the completion and acceptance of the work when you’re finished. If you have
“fuzzy” WBS levels or work packages, you won’t be able to determine status accurately.
In the information technology field, we have a saying about the status of projects: “It’s
90 percent complete.” The problem is it always seems that the last 10 percent takes twice
as long to complete as the first 90 did. If you’ve taken the time to document a WBS,
you’ll have a much better idea of what that 90 percent constitutes. The last step is the
verification step where you determine whether everything you’ve identified in the WBS is
absolutely necessary to fulfill the work of the project and whether it’s decomposed enough
to adequately describe the work. It has been my experience that documenting the WBS will
save you time later in the Planning processes, particularly developing the project schedule
and determining the project budget.
I believe the most important idea to take from this chapter is a simple one: Always use a
scope statement and requirements document, and always get them signed.
Summary
This chapter started you on the road to project planning via the Develop Project
Management Plan process, the Plan Scope Management process, the Collect Requirements
process, the Define Scope process, and the Create WBS process. We covered a lot of
material in this chapter. Everything you’ve learned so far becomes the foundation for
further project planning.
Heldman, Kim. PMP: Project Management Professional Exam Study Guide : Updated for the 2015 Exam, John Wiley & Sons, Incorporated, 2015. ProQuest
Ebook Central, http://ebookcentral.proquest.com/lib/gcu/detail.action?docID=4185201.
Created from gcu on 2021-09-30 17:08:46.
C
o
p
yr
ig
h
t
©
2
0
1
5
.
Jo
h
n
W
ile
y
&
S
o
n
s,
I
n
co
rp
o
ra
te
d
.
A
ll
ri
g
h
ts
r
e
se
rv
e
d
.
Exam Essentials 143
The output of the Develop Project Management Plan process is the project management
plan, which is concerned with defining, coordinating, and integrating all the ancillary
project plans and baselines. The purpose of this plan is to define how the project is
executed, how it’s monitored and controlled, and how it’s closed.
The primary output of the Plan Scope Management process is the scope management
plan. This plan is an element of the project management plan that describes how the project
team will go about defining project scope, validating the work of the project, and managing
and controlling scope.
The Collect Requirements process involves gathering and documenting the requirements
of the project. It’s important that requirements be measurable, traceable, testable, and so on.
Measurement criteria for project requirements are agreed upon by the stakeholders and project
manager. Additionally, requirements should be tracked in a traceability matrix that documents
where they originated, the results of the tests, the priority of the requirement, and more.
The project scope statement is produced during the Define Scope process. It describes
the project deliverables. The scope statement, along with the WBS and WBS dictionary,
forms the scope baseline that you’ll use to weigh future project decisions, most particularly
change requests. The scope statement contains a list of project deliverables that will be used
in future Planning processes.
The project scope statement contains many elements, including product scope
description, product acceptance criteria, deliverables, exclusions from scope, constraints,
and assumptions.
Constraints restrict or dictate the actions of the project team. Constraints usually
involve time, cost, and scope but can also include schedules, technology, quality, resources,
risk, and more.
Assumptions are things believed to be true. You’ll want to document project
assumptions and validate them as the project progresses.
A WBS is a deliverable‐oriented hierarchy of project essentials. The highest levels of
the WBS are described using nouns, and the lowest levels are described with verbs. Each
element in the WBS has its own set of objectives and deliverables that must be met in order
to fulfill the deliverables of the next highest level and ultimately the project itself. In this
way, the WBS validates the completeness of the work.
The lowest level of the WBS is known as the work package level. This breakdown allows
the project manager to determine cost estimates, time estimates, resource assignments, and
quality controls.
Exam Essentials
Be able to state the purpose of the Develop Project Management Plan process. It defines,
coordinates, and integrates all subsidiary project plans.
Understand the purpose of the project scope statement. The scope statement serves as a
common understanding of project scope among the stakeholders. The project objectives
Heldman, Kim. PMP: Project Management Professional Exam Study Guide : Updated for the 2015 Exam, John Wiley & Sons, Incorporated, 2015. ProQuest
Ebook Central, http://ebookcentral.proquest.com/lib/gcu/detail.action?docID=4185201.
Created from gcu on 2021-09-30 17:08:46.
C
o
p
yr
ig
h
t
©
2
0
1
5
.
Jo
h
n
W
ile
y
&
S
o
n
s,
I
n
co
rp
o
ra
te
d
.
A
ll
ri
g
h
ts
r
e
se
rv
e
d
.
General Requirements:
Reread the Kitchen Heaven Project Case Study in Heldman et al. pages 84-87, 139-141, 190-193, and 283-285.
Part 1: Action Steps
For each activity listed in the Action Steps section in the Logical Framework template complete the Resources, Budget (if given in the case), and Due Dates.
Add anticipated resources for each action step/activity. Include all types of resources including human, technical, and physical resources.
Add budget information as provided in the case. If budget information not specifically provided in the case, no budget information is required.
Estimate potential due dates for each action step/activity. These estimates should support the planned/expected end date of the project as defined in the case. Document assumptions made in setting the due dates.
Part 2: RACI Matrix
Complete the RACI Matrix Template. Add rows as needed.
Each action step/activity must be listed in the RACI matrix.
Part 3: PowerPoint Presentation
Create a short 3-minute presentation discussing the final Logical Framework and how the proposal meets the Goals presented in the case.
The time limit is 3 minutes. No longer.
A maximum of three slides not including the cover and reference slide.
Speaker notes are expected.
CATEGORIES
Economics
Nursing
Applied Sciences
Psychology
Science
Management
Computer Science
Human Resource Management
Accounting
Information Systems
English
Anatomy
Operations Management
Sociology
Literature
Education
Business & Finance
Marketing
Engineering
Statistics
Biology
Political Science
Reading
History
Financial markets
Philosophy
Mathematics
Law
Criminal
Architecture and Design
Government
Social Science
World history
Chemistry
Humanities
Business Finance
Writing
Programming
Telecommunications Engineering
Geography
Physics
Spanish
ach
e. Embedded Entrepreneurship
f. Three Social Entrepreneurship Models
g. Social-Founder Identity
h. Micros-enterprise Development
Outcomes
Subset 2. Indigenous Entrepreneurship Approaches (Outside of Canada)
a. Indigenous Australian Entrepreneurs Exami
Calculus
(people influence of
others) processes that you perceived occurs in this specific Institution Select one of the forms of stratification highlighted (focus on inter the intersectionalities
of these three) to reflect and analyze the potential ways these (
American history
Pharmacology
Ancient history
. Also
Numerical analysis
Environmental science
Electrical Engineering
Precalculus
Physiology
Civil Engineering
Electronic Engineering
ness Horizons
Algebra
Geology
Physical chemistry
nt
When considering both O
lassrooms
Civil
Probability
ions
Identify a specific consumer product that you or your family have used for quite some time. This might be a branded smartphone (if you have used several versions over the years)
or the court to consider in its deliberations. Locard’s exchange principle argues that during the commission of a crime
Chemical Engineering
Ecology
aragraphs (meaning 25 sentences or more). Your assignment may be more than 5 paragraphs but not less.
INSTRUCTIONS:
To access the FNU Online Library for journals and articles you can go the FNU library link here:
https://www.fnu.edu/library/
In order to
n that draws upon the theoretical reading to explain and contextualize the design choices. Be sure to directly quote or paraphrase the reading
ce to the vaccine. Your campaign must educate and inform the audience on the benefits but also create for safe and open dialogue. A key metric of your campaign will be the direct increase in numbers.
Key outcomes: The approach that you take must be clear
Mechanical Engineering
Organic chemistry
Geometry
nment
Topic
You will need to pick one topic for your project (5 pts)
Literature search
You will need to perform a literature search for your topic
Geophysics
you been involved with a company doing a redesign of business processes
Communication on Customer Relations. Discuss how two-way communication on social media channels impacts businesses both positively and negatively. Provide any personal examples from your experience
od pressure and hypertension via a community-wide intervention that targets the problem across the lifespan (i.e. includes all ages).
Develop a community-wide intervention to reduce elevated blood pressure and hypertension in the State of Alabama that in
in body of the report
Conclusions
References (8 References Minimum)
*** Words count = 2000 words.
*** In-Text Citations and References using Harvard style.
*** In Task section I’ve chose (Economic issues in overseas contracting)"
Electromagnetism
w or quality improvement; it was just all part of good nursing care. The goal for quality improvement is to monitor patient outcomes using statistics for comparison to standards of care for different diseases
e a 1 to 2 slide Microsoft PowerPoint presentation on the different models of case management. Include speaker notes... .....Describe three different models of case management.
visual representations of information. They can include numbers
SSAY
ame workbook for all 3 milestones. You do not need to download a new copy for Milestones 2 or 3. When you submit Milestone 3
pages):
Provide a description of an existing intervention in Canada
making the appropriate buying decisions in an ethical and professional manner.
Topic: Purchasing and Technology
You read about blockchain ledger technology. Now do some additional research out on the Internet and share your URL with the rest of the class
be aware of which features their competitors are opting to include so the product development teams can design similar or enhanced features to attract more of the market. The more unique
low (The Top Health Industry Trends to Watch in 2015) to assist you with this discussion.
https://youtu.be/fRym_jyuBc0
Next year the $2.8 trillion U.S. healthcare industry will finally begin to look and feel more like the rest of the business wo
evidence-based primary care curriculum. Throughout your nurse practitioner program
Vignette
Understanding Gender Fluidity
Providing Inclusive Quality Care
Affirming Clinical Encounters
Conclusion
References
Nurse Practitioner Knowledge
Mechanics
and word limit is unit as a guide only.
The assessment may be re-attempted on two further occasions (maximum three attempts in total). All assessments must be resubmitted 3 days within receiving your unsatisfactory grade. You must clearly indicate “Re-su
Trigonometry
Article writing
Other
5. June 29
After the components sending to the manufacturing house
1. In 1972 the Furman v. Georgia case resulted in a decision that would put action into motion. Furman was originally sentenced to death because of a murder he committed in Georgia but the court debated whether or not this was a violation of his 8th amend
One of the first conflicts that would need to be investigated would be whether the human service professional followed the responsibility to client ethical standard. While developing a relationship with client it is important to clarify that if danger or
Ethical behavior is a critical topic in the workplace because the impact of it can make or break a business
No matter which type of health care organization
With a direct sale
During the pandemic
Computers are being used to monitor the spread of outbreaks in different areas of the world and with this record
3. Furman v. Georgia is a U.S Supreme Court case that resolves around the Eighth Amendments ban on cruel and unsual punishment in death penalty cases. The Furman v. Georgia case was based on Furman being convicted of murder in Georgia. Furman was caught i
One major ethical conflict that may arise in my investigation is the Responsibility to Client in both Standard 3 and Standard 4 of the Ethical Standards for Human Service Professionals (2015). Making sure we do not disclose information without consent ev
4. Identify two examples of real world problems that you have observed in your personal
Summary & Evaluation: Reference & 188. Academic Search Ultimate
Ethics
We can mention at least one example of how the violation of ethical standards can be prevented. Many organizations promote ethical self-regulation by creating moral codes to help direct their business activities
*DDB is used for the first three years
For example
The inbound logistics for William Instrument refer to purchase components from various electronic firms. During the purchase process William need to consider the quality and price of the components. In this case
4. A U.S. Supreme Court case known as Furman v. Georgia (1972) is a landmark case that involved Eighth Amendment’s ban of unusual and cruel punishment in death penalty cases (Furman v. Georgia (1972)
With covid coming into place
In my opinion
with
Not necessarily all home buyers are the same! When you choose to work with we buy ugly houses Baltimore & nationwide USA
The ability to view ourselves from an unbiased perspective allows us to critically assess our personal strengths and weaknesses. This is an important step in the process of finding the right resources for our personal learning style. Ego and pride can be
· By Day 1 of this week
While you must form your answers to the questions below from our assigned reading material
CliftonLarsonAllen LLP (2013)
5 The family dynamic is awkward at first since the most outgoing and straight forward person in the family in Linda
Urien
The most important benefit of my statistical analysis would be the accuracy with which I interpret the data. The greatest obstacle
From a similar but larger point of view
4 In order to get the entire family to come back for another session I would suggest coming in on a day the restaurant is not open
When seeking to identify a patient’s health condition
After viewing the you tube videos on prayer
Your paper must be at least two pages in length (not counting the title and reference pages)
The word assimilate is negative to me. I believe everyone should learn about a country that they are going to live in. It doesnt mean that they have to believe that everything in America is better than where they came from. It means that they care enough
Data collection
Single Subject Chris is a social worker in a geriatric case management program located in a midsize Northeastern town. She has an MSW and is part of a team of case managers that likes to continuously improve on its practice. The team is currently using an
I would start off with Linda on repeating her options for the child and going over what she is feeling with each option. I would want to find out what she is afraid of. I would avoid asking her any “why” questions because I want her to be in the here an
Summarize the advantages and disadvantages of using an Internet site as means of collecting data for psychological research (Comp 2.1) 25.0\% Summarization of the advantages and disadvantages of using an Internet site as means of collecting data for psych
Identify the type of research used in a chosen study
Compose a 1
Optics
effect relationship becomes more difficult—as the researcher cannot enact total control of another person even in an experimental environment. Social workers serve clients in highly complex real-world environments. Clients often implement recommended inte
I think knowing more about you will allow you to be able to choose the right resources
Be 4 pages in length
soft MB-920 dumps review and documentation and high-quality listing pdf MB-920 braindumps also recommended and approved by Microsoft experts. The practical test
g
One thing you will need to do in college is learn how to find and use references. References support your ideas. College-level work must be supported by research. You are expected to do that for this paper. You will research
Elaborate on any potential confounds or ethical concerns while participating in the psychological study 20.0\% Elaboration on any potential confounds or ethical concerns while participating in the psychological study is missing. Elaboration on any potenti
3 The first thing I would do in the family’s first session is develop a genogram of the family to get an idea of all the individuals who play a major role in Linda’s life. After establishing where each member is in relation to the family
A Health in All Policies approach
Note: The requirements outlined below correspond to the grading criteria in the scoring guide. At a minimum
Chen
Read Connecting Communities and Complexity: A Case Study in Creating the Conditions for Transformational Change
Read Reflections on Cultural Humility
Read A Basic Guide to ABCD Community Organizing
Use the bolded black section and sub-section titles below to organize your paper. For each section
Losinski forwarded the article on a priority basis to Mary Scott
Losinksi wanted details on use of the ED at CGH. He asked the administrative resident