planning the project - Management
Reflection and Discussion Forum Week 5 Reflection and Discussion Forum Week 5Assigned Readings:Chapter 11: Resource PlanningChapter 12: Budget PlanningInitial Postings: Read and reflect on the assigned readings for the week. Then post what you thought was the most important concept(s), method(s), term(s), and/or any other thing that you felt was worthy of your understanding in each assigned textbook chapter.Your initial post should be based upon the assigned reading for the week, so the textbook should be a source listed in your reference section and cited within the body of the text. Other sources are not required but feel free to use them if they aid in your discussion.Also, provide a graduate-level response to each of the following questions: How would a cost management plan address the challenges of managing project costs within the internal financial procedures and accounting codes of an organization? What benefits do budgeting processes bring to projects, and what weaknesses do they possess? [Your post must be substantive and demonstrate insight gained from the course material. Postings must be in the student's own words - do not provide quotes!] [Your initial post should be at least 450+ words and in APA format (including Times New Roman with font size 12 and double spaced). Post the actual body of your paper in the discussion thread then attach a Word version of the paper for APA review]    Problem Set #5 Earned-value analysis. A project budget calls for the following expenditures:TaskDateBudgeted AmountBuild formsApril 1$10,000Pour foundationApril 1$50,000May 1$100,000Frame wallsMay 1$30,000June 1$30,000Remaining tasksJuly 1 and beyond$500,000 Define each term in your own words, calculate these values for the above project, and show your work: Budgeted cost baseline (make a graph illustrating this one) Budget at completion (BAC) Planned value (PV) as of May 1 Earned value (EV) as of May 1 if the foundation work is only two-thirds complete. Everything else is on schedule. SV as of May 1. Actual cost as of May 1 is $160,000. Calculate the cost variance (CV) as of May 1. Schedule performance index (SPI) Cost performance index (CPI) Estimate to complete (ETC), assuming that the previous cost variances will not affect future costs Estimate at completion (EAC) Resource Planning This work is licensed under a Creative Commons Attribution 3.0 Unported License (CC-BY). Project Management Chapter 11: Resource Planning 1 Resource Planning Importance Relationship to Schedule Planning Human Resources Other Resources This work is licensed under a Creative Commons Attribution 3.0 Unported License (CC-BY). Project Management Chapter 11: Resource Planning Resource Planning After you have created the first draft of your schedule, an important step is to identify the resources required Sometimes the same resource is needed for two different tasks, so they cannot be carried out concurrently Resources include Human resources Other resources such as equipment, office space, computer hardware or software, construction materials This work is licensed under a Creative Commons Attribution 3.0 Unported License (CC-BY). Project Management Chapter 11: Resource Planning Relationship Between Schedule Planning and Resource Planning Based on the WBS, the PM and team have prepared the initial draft of the schedule This is a key step If you don’t yet understand the scheduling part of the planning process, review it before proceeding to resource planning This work is licensed under a Creative Commons Attribution 3.0 Unported License (CC-BY). Project Management Chapter 11: Resource Planning Estimating—tools and techniques Expert judgment Alternative analysis Published estimating data Project management software Bottom-up estimating This work is licensed under a Creative Commons Attribution 3.0 Unported License (CC-BY). Project Management Chapter 11: Resource Planning Resource Leveling If two or more concurrent activities need to use the same resources, the schedule may need to be adjusted If a very expensive piece of equipment such as a crane is required, the tasks may have to be rescheduled consecutively rather than concurrently This can also happen due to staff requirements Software such as MS Project has resource leveling tools This work is licensed under a Creative Commons Attribution 3.0 Unported License (CC-BY). Project Management Chapter 11: Resource Planning The mythical man-month What is the impact of adding people to a project that is struggling to meet deadlines? This work is licensed under a Creative Commons Attribution 3.0 Unported License (CC-BY). Project Management Chapter 11: Resource Planning HR Planning The most important resource is the people Select the right people Technically skilled Motivated Provide them with the resources and training they need Nurture them—provide compensation and recognition Deal with issues promptly and as directly as possible This work is licensed under a Creative Commons Attribution 3.0 Unported License (CC-BY). Project Management Chapter 11: Resource Planning The person-day The work of one person for one day is a person-day You may also work with person-hours Think about how easy or difficult it is to substitute one person for ten days in place of ten people for one day on different tasks: Installing ten dozen new PCs on desktops in an office area Configuring the server which the PCs will use for file and print sharing Creating a new computer game Pouring a foundation Building the forms into which the foundation will be poured This work is licensed under a Creative Commons Attribution 3.0 Unported License (CC-BY). Project Management Chapter 11: Resource Planning Typical project team roles Project Manager Developer Engineer Subject matter expert Team members Customer / client representative This work is licensed under a Creative Commons Attribution 3.0 Unported License (CC-BY). Project Management Chapter 11: Resource Planning The HR environment Laws Employment regulations such as wage legislation, holidays Health and safety Culture Organizational standards Collective Agreements This work is licensed under a Creative Commons Attribution 3.0 Unported License (CC-BY). Project Management Chapter 11: Resource Planning Employee performance management Employee performance employee’s work results such as quality or quantity of outputs, work behavior (such as punctuality) job-related attributes (such as cooperation and initiative) After conducting employee performance reviews managers should: provide feedback to employees about how well they have performed on established goals provide feedback to employees about areas in which the subordinate is weak or could do better take corrective action to address problems with employees performing at or below the minimum expectations reward superior performers to encourage their continued excellence This work is licensed under a Creative Commons Attribution 3.0 Unported License (CC-BY). Project Management Chapter 11: Resource Planning Rewards for employees Discuss This work is licensed under a Creative Commons Attribution 3.0 Unported License (CC-BY). Project Management Chapter 11: Resource Planning Maslow’s Hierarchy of Needs Physiological Safety Love/belonging Esteem Self-actualization This work is licensed under a Creative Commons Attribution 3.0 Unported License (CC-BY). Project Management Chapter 11: Resource Planning Emotional Intelligence Self-awareness Self-regulation Empathy Relationship management This work is licensed under a Creative Commons Attribution 3.0 Unported License (CC-BY). Project Management Chapter 11: Resource Planning Personality Types Myers-Briggs: four dimensions: Extroversion <–> Introversion Sensing <–> Intuition Thinking <–> Feeling Judging <–> Perceiving Sixteen personality types can be derived from the four dimensions Generally, a MIX of personality types on a project brings strength Knowing your own type and the types of other team members can help people work together This work is licensed under a Creative Commons Attribution 3.0 Unported License (CC-BY). Project Management Chapter 11: Resource Planning Dimensions of Leadership Robert Tannenbaum and Warren Schmidt leaders are either autocratic or democratic Harold Leavitt leaders are pathfinders (visionaries), problem solvers (analytical), or implementers (team oriented) James MacGregor Burns leaders are either transactional (focused on actions and decisions) or transformational (focused on the long-term needs of the group and organization) Fred Fiedler contingency theory, the ability of leaders to adapt This work is licensed under a Creative Commons Attribution 3.0 Unported License (CC-BY). Project Management Chapter 11: Resource Planning Negotiation A key project management skill Frequently, PMs have accountability but may have limited authority Matrix management structure Subject matter experts Negotiating with Other managers Suppliers Customers Others This work is licensed under a Creative Commons Attribution 3.0 Unported License (CC-BY). Project Management Chapter 11: Resource Planning Conflict Conflict is not a bad thing—it can be healthy for people to be able to express differences about how to approach the work Conflict-resolution styles: Avoiding Forcing Collaborating Compromising Accommodating This work is licensed under a Creative Commons Attribution 3.0 Unported License (CC-BY). Project Management Chapter 11: Resource Planning Delegation PM is not expected to DO all the work Must identify and clearly assign work to others on the team Make expectations clear Recognize performance Follow through This work is licensed under a Creative Commons Attribution 3.0 Unported License (CC-BY). Project Management Chapter 11: Resource Planning Resource management techniques Resource leveling Objective is 100% utilization Software can help This work is licensed under a Creative Commons Attribution 3.0 Unported License (CC-BY). Project Management Chapter 11: Resource Planning Resource Planning Summary Planning for resource utilization is a key process in preparing a project plan Resource planning follows the first draft of the schedule and impacts the schedule Resources include human resources and other resources Managing human resources includes hiring, training, motivating, rewarding A number of models can be used to help the team work together There are several theories of leadership; leadership is more than issuing directives This work is licensed under a Creative Commons Attribution 3.0 Unported License (CC-BY). Project Management Chapter 11: Resource Planning Questions? This work is licensed under a Creative Commons Attribution 3.0 Unported License (CC-BY). Project Management Chapter 11: Resource Planning 23 Budget Planning This work is licensed under a Creative Commons Attribution 3.0 Unported License (CC-BY). Project Management Chapter 12: Budget Planning 1 Budget Management Importance Estimating costs to compare and select Methods of Estimating Managing the Budget Budget timeline Budget variances This work is licensed under a Creative Commons Attribution 3.0 Unported License (CC-BY). Project Management Chapter 12: Budget Planning Importance of budget planning Cost is one of the three project constraints A budget is a plan or forecast Cost management also includes tracking and managing variances from the planned expenditures Detailed estimates are important This work is licensed under a Creative Commons Attribution 3.0 Unported License (CC-BY). Project Management Chapter 12: Budget Planning Estimating costs to compare and select projects Payback, rate of return or NPV (or combine them) Need accurate numbers but must balance with the cost of getting more accurate estimates This work is licensed under a Creative Commons Attribution 3.0 Unported License (CC-BY). Project Management Chapter 12: Budget Planning Estimating methods Analogous estimate Find a similar project or task and assume this one will be the same or similar The more experience the estimator has, the better this works Learn from each project DPCI (Darnell-Preston Complexity Index) can help with benchmarking Parametric estimate Parameters such as number of square feet for a building; number of kitchens, bathrooms, etc. for a house. Bottom-up estimating Estimate each item or task and add them together Generally more accurate but takes more effort to create This work is licensed under a Creative Commons Attribution 3.0 Unported License (CC-BY). Project Management Chapter 12: Budget Planning Estimating Guidelines Don’t gold-plate: estimate what you expect, and meet that estimate. This work is licensed under a Creative Commons Attribution 3.0 Unported License (CC-BY). Project Management Chapter 12: Budget Planning Managing the Budget Cash flow Make a plan of WHEN the outflows will occur, and ensure that the money is available on time Contingency reserves For unexpected expenses that arise during the project There are almost always some surprises, but can’t predict at the start what it will be Project Manager does not allocate to the sub-projects but manages it centrally Can be spent and still be within the original project budget Management Reserves For scope changes Not likely to be spent; not part of project baseline This work is licensed under a Creative Commons Attribution 3.0 Unported License (CC-BY). Project Management Chapter 12: Budget Planning Reporting Progress: Earned value management Budgeted Cost of work Scheduled BCWS Detailed estimates for each activity in the project Planned Value PV Total budgeted cost as of a certain date in the project Earned Value EV Budgeted cost of the completed work as of a certain date in the project Actual Cost AC Actual cost of the completed work as of a certain date in the project Budget at Completion BAC Total budgeted costs for the entire project This work is licensed under a Creative Commons Attribution 3.0 Unported License (CC-BY). Project Management Chapter 12: Budget Planning Project Cost Chart BAC This work is licensed under a Creative Commons Attribution 3.0 Unported License (CC-BY). Project Management Chapter 12: Budget Planning Budget Baseline February March April May June July 10000 12000 22000 30000 40000 45000 Budget Baseline and Project Cost Chart The project budget is usually shown graphically, illustrating the cumulative planned spending. Typical shape for the budget curve is s-shaped, with less spending at the beginning and end of the project. Add the periodic expenditures on a regular basis to create the Project Cost Chart. This work is licensed under a Creative Commons Attribution 3.0 Unported License (CC-BY). Project Management Chapter 12: Budget Planning Project Cost Chart (up to May) BAC AC This work is licensed under a Creative Commons Attribution 3.0 Unported License (CC-BY). Project Management Chapter 12: Budget Planning Actual Expenditures February March April May June July 5000 7000 30000 35000 Bud get Baseline February March April May June July 10000 12000 22000 30000 40000 45000 Schedule Variance: SV Difference between planned and actual progress SV=EV-PV Positive value: project is ahead of schedule Zero: project is on-time Negative: project is behind schedule This work is licensed under a Creative Commons Attribution 3.0 Unported License (CC-BY). Project Management Chapter 12: Budget Planning Cost Variance: CV The difference between the earned value and the actual cost is the cost variance: CV=EV-AC If positive, you are achieving more than you predicted for the money If zero, you are right on the plan If negative, you are achieving less than you predicted for the money This work is licensed under a Creative Commons Attribution 3.0 Unported License (CC-BY). Project Management Chapter 12: Budget Planning Schedule Performance Index: SPI Compares progress on the scope to spending: SPI = EV/PV SPI less than one indicates the project is behind schedule SPI of one is right on schedule SPI greater than one the project is ahead of schedule This work is licensed under a Creative Commons Attribution 3.0 Unported License (CC-BY). Project Management Chapter 12: Budget Planning Cost Performance Index: CPI Compares the budget spent to date with progress to date: CPI=EV/AC A value greater than one: under budget Equal to one: on budget Less than one: overspending the budget This work is licensed under a Creative Commons Attribution 3.0 Unported License (CC-BY). Project Management Chapter 12: Budget Planning Estimated Cost to Complete the Project: ETC Formula to use depends on what the PM expects with regard to future project costs and whether the original budget assumptions remain valid This work is licensed under a Creative Commons Attribution 3.0 Unported License (CC-BY). Project Management Chapter 12: Budget Planning ETC if past variances are not expected to continue: ETC = BAC – EV This work is licensed under a Creative Commons Attribution 3.0 Unported License (CC-BY). Project Management Chapter 12: Budget Planning ETC if past variances are expected to continue at the same level ETC = (BAC – EV)/CPI This work is licensed under a Creative Commons Attribution 3.0 Unported License (CC-BY). Project Management Chapter 12: Budget Planning Estimated Final Project Cost: EAC EAC = ETC + AC This work is licensed under a Creative Commons Attribution 3.0 Unported License (CC-BY). Project Management Chapter 12: Budget Planning Budget Timeline Contractual agreements often require partial payments Prepare a schedule, based on contractual and other expenditure requirements This work is licensed under a Creative Commons Attribution 3.0 Unported License (CC-BY). Project Management Chapter 12: Budget Planning Budget Management Summary Cost estimations may be used to choose between options Managing the budget includes Estimating costs and setting a budget Determining when the budgeted costs should occur Tracking expenditures Managing variances between the budget and the expenditures Methods of Estimating Analogous, Parametric, Bottom-up Managing the Budget Budget timeline Budget variances This work is licensed under a Creative Commons Attribution 3.0 Unported License (CC-BY). Project Management Chapter 12: Budget Planning Budget Management Summary (continued) Budgeting and Cost Management are important activities for project managers There are several methods for estimating the costs Estimated costs may be used to choose between options Project progress and budget management are closely related and can be managed with indices: BCWS, PV, SV, AC, CV, SPI, CPI, ETC, BAC and EAC Contingency funds allow for the unexpected Reporting to the team and to management are important components in budget management This work is licensed under a Creative Commons Attribution 3.0 Unported License (CC-BY). Project Management Chapter 12: Budget Planning Questions? This work is licensed under a Creative Commons Attribution 3.0 Unported License (CC-BY). Project Management Chapter 12: Budget Planning 23
CATEGORIES
Economics Nursing Applied Sciences Psychology Science Management Computer Science Human Resource Management Accounting Information Systems English Anatomy Operations Management Sociology Literature Education Business & Finance Marketing Engineering Statistics Biology Political Science Reading History Financial markets Philosophy Mathematics Law Criminal Architecture and Design Government Social Science World history Chemistry Humanities Business Finance Writing Programming Telecommunications Engineering Geography Physics Spanish ach e. Embedded Entrepreneurship f. Three Social Entrepreneurship Models g. Social-Founder Identity h. Micros-enterprise Development Outcomes Subset 2. Indigenous Entrepreneurship Approaches (Outside of Canada) a. Indigenous Australian Entrepreneurs Exami Calculus (people influence of  others) processes that you perceived occurs in this specific Institution Select one of the forms of stratification highlighted (focus on inter the intersectionalities  of these three) to reflect and analyze the potential ways these ( American history Pharmacology Ancient history . Also Numerical analysis Environmental science Electrical Engineering Precalculus Physiology Civil Engineering Electronic Engineering ness Horizons Algebra Geology Physical chemistry nt When considering both O lassrooms Civil Probability ions Identify a specific consumer product that you or your family have used for quite some time. This might be a branded smartphone (if you have used several versions over the years) or the court to consider in its deliberations. Locard’s exchange principle argues that during the commission of a crime Chemical Engineering Ecology aragraphs (meaning 25 sentences or more). Your assignment may be more than 5 paragraphs but not less. INSTRUCTIONS:  To access the FNU Online Library for journals and articles you can go the FNU library link here:  https://www.fnu.edu/library/ In order to n that draws upon the theoretical reading to explain and contextualize the design choices. Be sure to directly quote or paraphrase the reading ce to the vaccine. Your campaign must educate and inform the audience on the benefits but also create for safe and open dialogue. A key metric of your campaign will be the direct increase in numbers.  Key outcomes: The approach that you take must be clear Mechanical Engineering Organic chemistry Geometry nment Topic You will need to pick one topic for your project (5 pts) Literature search You will need to perform a literature search for your topic Geophysics you been involved with a company doing a redesign of business processes Communication on Customer Relations. Discuss how two-way communication on social media channels impacts businesses both positively and negatively. Provide any personal examples from your experience od pressure and hypertension via a community-wide intervention that targets the problem across the lifespan (i.e. includes all ages). Develop a community-wide intervention to reduce elevated blood pressure and hypertension in the State of Alabama that in in body of the report Conclusions References (8 References Minimum) *** Words count = 2000 words. *** In-Text Citations and References using Harvard style. *** In Task section I’ve chose (Economic issues in overseas contracting)" Electromagnetism w or quality improvement; it was just all part of good nursing care.  The goal for quality improvement is to monitor patient outcomes using statistics for comparison to standards of care for different diseases e a 1 to 2 slide Microsoft PowerPoint presentation on the different models of case management.  Include speaker notes... .....Describe three different models of case management. visual representations of information. They can include numbers SSAY ame workbook for all 3 milestones. You do not need to download a new copy for Milestones 2 or 3. When you submit Milestone 3 pages): Provide a description of an existing intervention in Canada making the appropriate buying decisions in an ethical and professional manner. Topic: Purchasing and Technology You read about blockchain ledger technology. Now do some additional research out on the Internet and share your URL with the rest of the class be aware of which features their competitors are opting to include so the product development teams can design similar or enhanced features to attract more of the market. The more unique low (The Top Health Industry Trends to Watch in 2015) to assist you with this discussion.         https://youtu.be/fRym_jyuBc0 Next year the $2.8 trillion U.S. healthcare industry will   finally begin to look and feel more like the rest of the business wo evidence-based primary care curriculum. Throughout your nurse practitioner program Vignette Understanding Gender Fluidity Providing Inclusive Quality Care Affirming Clinical Encounters Conclusion References Nurse Practitioner Knowledge Mechanics and word limit is unit as a guide only. The assessment may be re-attempted on two further occasions (maximum three attempts in total). All assessments must be resubmitted 3 days within receiving your unsatisfactory grade. You must clearly indicate “Re-su Trigonometry Article writing Other 5. June 29 After the components sending to the manufacturing house 1. In 1972 the Furman v. Georgia case resulted in a decision that would put action into motion. Furman was originally sentenced to death because of a murder he committed in Georgia but the court debated whether or not this was a violation of his 8th amend One of the first conflicts that would need to be investigated would be whether the human service professional followed the responsibility to client ethical standard.  While developing a relationship with client it is important to clarify that if danger or Ethical behavior is a critical topic in the workplace because the impact of it can make or break a business No matter which type of health care organization With a direct sale During the pandemic Computers are being used to monitor the spread of outbreaks in different areas of the world and with this record 3. Furman v. Georgia is a U.S Supreme Court case that resolves around the Eighth Amendments ban on cruel and unsual punishment in death penalty cases. The Furman v. Georgia case was based on Furman being convicted of murder in Georgia. Furman was caught i One major ethical conflict that may arise in my investigation is the Responsibility to Client in both Standard 3 and Standard 4 of the Ethical Standards for Human Service Professionals (2015).  Making sure we do not disclose information without consent ev 4. Identify two examples of real world problems that you have observed in your personal Summary & Evaluation: Reference & 188. Academic Search Ultimate Ethics We can mention at least one example of how the violation of ethical standards can be prevented. Many organizations promote ethical self-regulation by creating moral codes to help direct their business activities *DDB is used for the first three years For example The inbound logistics for William Instrument refer to purchase components from various electronic firms. During the purchase process William need to consider the quality and price of the components. In this case 4. A U.S. Supreme Court case known as Furman v. Georgia (1972) is a landmark case that involved Eighth Amendment’s ban of unusual and cruel punishment in death penalty cases (Furman v. Georgia (1972) With covid coming into place In my opinion with Not necessarily all home buyers are the same! When you choose to work with we buy ugly houses Baltimore & nationwide USA The ability to view ourselves from an unbiased perspective allows us to critically assess our personal strengths and weaknesses. This is an important step in the process of finding the right resources for our personal learning style. Ego and pride can be · By Day 1 of this week While you must form your answers to the questions below from our assigned reading material CliftonLarsonAllen LLP (2013) 5 The family dynamic is awkward at first since the most outgoing and straight forward person in the family in Linda Urien The most important benefit of my statistical analysis would be the accuracy with which I interpret the data. The greatest obstacle From a similar but larger point of view 4 In order to get the entire family to come back for another session I would suggest coming in on a day the restaurant is not open When seeking to identify a patient’s health condition After viewing the you tube videos on prayer Your paper must be at least two pages in length (not counting the title and reference pages) The word assimilate is negative to me. I believe everyone should learn about a country that they are going to live in. It doesnt mean that they have to believe that everything in America is better than where they came from. It means that they care enough Data collection Single Subject Chris is a social worker in a geriatric case management program located in a midsize Northeastern town. She has an MSW and is part of a team of case managers that likes to continuously improve on its practice. The team is currently using an I would start off with Linda on repeating her options for the child and going over what she is feeling with each option.  I would want to find out what she is afraid of.  I would avoid asking her any “why” questions because I want her to be in the here an Summarize the advantages and disadvantages of using an Internet site as means of collecting data for psychological research (Comp 2.1) 25.0\% Summarization of the advantages and disadvantages of using an Internet site as means of collecting data for psych Identify the type of research used in a chosen study Compose a 1 Optics effect relationship becomes more difficult—as the researcher cannot enact total control of another person even in an experimental environment. Social workers serve clients in highly complex real-world environments. Clients often implement recommended inte I think knowing more about you will allow you to be able to choose the right resources Be 4 pages in length soft MB-920 dumps review and documentation and high-quality listing pdf MB-920 braindumps also recommended and approved by Microsoft experts. The practical test g One thing you will need to do in college is learn how to find and use references. References support your ideas. College-level work must be supported by research. You are expected to do that for this paper. You will research Elaborate on any potential confounds or ethical concerns while participating in the psychological study 20.0\% Elaboration on any potential confounds or ethical concerns while participating in the psychological study is missing. Elaboration on any potenti 3 The first thing I would do in the family’s first session is develop a genogram of the family to get an idea of all the individuals who play a major role in Linda’s life. After establishing where each member is in relation to the family A Health in All Policies approach Note: The requirements outlined below correspond to the grading criteria in the scoring guide. At a minimum Chen Read Connecting Communities and Complexity: A Case Study in Creating the Conditions for Transformational Change Read Reflections on Cultural Humility Read A Basic Guide to ABCD Community Organizing Use the bolded black section and sub-section titles below to organize your paper. For each section Losinski forwarded the article on a priority basis to Mary Scott Losinksi wanted details on use of the ED at CGH. He asked the administrative resident