Project Management_Scope and Schedule - Management
The project will address client’s needs to upgrade their 3 existing legacy data centers and migrate eligible applications to the Cloud:
Total of 3 primary data centers (2 for Production and 1 for Disaster Recovery)
All 3 data centers share redundant WAN circuits (2 MPLS and 1 Point-2Point) for users and data traffic
Client has a total of 145 enterprise applications and 1350 servers:
450 Windows Servers
550 Unix Servers
350 ESX, VMWare, and legacy AIX servers
Allowed project budget is $1.5 Million with a $150K for contengecies
The client is open to the top 3 Cloud providers (AWS, Azure, and Google Cloud)
You have the ability to assemble your team
Stakeholders are also open to your specific and project needs (define their roles and responsibilities as you see them
fit)
All 3 Data centers are in the United States – the DR DC must be on a different State for recovery purposes
Assignment
Week 4 – Scope and Schedule: At the end of week 4, you are to finalize the initial approved scope from week one an
d start building the project schedule. In this week, you are also to work on building the project Work-Breakdown Str
ucture (WBS). Project scope and schedule will include the following components:
Finalized project scope
Project requirements – in more details
WBS structure
Developed project schedule
Identify key milestones and deliverables
Outline project resources and assign them to tasks accordingly.
Stakeholder engagement – communication plan
NOTE: I have added project guide and work I have done so far, need help with rest of the sections in week4 and Feel free to edit the content
Course : :Project Management
Course Project
Overview:
This course project introduces an opportunity to explore all the project stages (from inception to closing) facilitated
by the well-known Project Management Group Processes (initiation, planning, execution, monitoring and control, an
d closure) as outlined in the PMBOK® Guide.
Two Project Options:
Data Center Transformation – to complete a migration strategy/plan to complete the following two tasks:
On-Premise Transformation
Infrastructure And Application Migration to The Cloud
Pick your own project:
Students will have the option to also choose their own project – project scope will need to be approved by the course
instructor
As you progress through the weekly materials in the course, you will apply the key principles and knowledge areas (
Scope, cost, schedule, quality, resources, risk management, procurement, communication, and stakeholder managem
ent) to your project. You will use Microsoft Project software to track the entire project management plan (PMP), dev
elop the schedule, and track the overall progress of the project. As the project manager (PM) for a medium-scale pro
ject, you will apply fundamental principles and best practices to conduct your project from inception to closing. Eac
h assignment provides further detail.
Known Scope:
The project will address client’s needs to upgrade their 3 existing legacy data centers and migrate eligible applicatio
ns to the Cloud:
Total of 3 primary data centers (2 for Production and 1 for Disaster Recovery)
All 3 data centers share redundant WAN circuits (2 MPLS and 1 Point-2Point) for users and data traffic
Client has a total of 145 enterprise applications and 1350 servers:
450 Windows Servers
550 Unix Servers
350 ESX, VMWare, and legacy AIX servers
Allowed project budget is $1.5 Million with a $150K for contengecies
The client is open to the top 3 Cloud providers (AWS, Azure, and Google Cloud)
You have the ability to assemble your team
Stakeholders are also open to your specific and project needs (define their roles and responsibilities as you see them
fit)
All 3 Data centers are in the United States – the DR DC must be on a different State for recovery purposes
Requirements:
Meet the weekly assignments’ requirements (total of 4 assignments to complete the entire project) within the 8 week
s duration of the course.
You will be assigned as the main PM for the project, where you will own the entire project
Your course instructor will act at the project sponsor – can address all your questions and concerns and will provide
you feedback during the weekly assignments submissions.
The project will include internal and external stakeholders, vendors, team members, and contractors.
A well-defined project charter must be approved by course instructor by end of week one.
Your final project management plan as well as the weekly submissions must adhere to the following formatting requ
irements:
APA version 7 is the required format for the entire paper.
Turnitin tool
Weekly Assignment - Structure:
Week 2 - Project Charter: At the end of week 2, you are to create and submit the project charter. This is the first offi
cial document to be reviewed and approved by the project sponsor. Project charter will include the following compo
nents:
High-level project scope
High-level project requirements
Business needs
Early estimation and forecasted cost
Stakeholder analysis (roles and responsibilities)
High-level Communication plan
High-Level Resource plan
Early risk indications
Week 4 – Scope and Schedule: At the end of week 4, you are to finalize the initial approved scope from week one an
d start building the project schedule. In this week, you are also to work on building the project Work-Breakdown Str
ucture (WBS). Project scope and schedule will include the following components:
Finalized project scope
Project requirements – in more details
WBS structure
Developed project schedule
Identify key milestones and deliverables
Outline project resources and assign them to tasks accordingly.
Stakeholder engagement – communication plan
Week 6 – Budget and Risk Management: At the end of week 6, you are to finalize the overall project cost and clearl
y document project risks gathered throughout the project. As part of risk management plan, you are expected to shar
e a risk response plan. Project cost and risk management plans will include the following components:
Overall project budget (utilizing EVM – share current and forecasted project status)
Project requirements – updated
Cost management plan – outlining contingency plan for project changes
Detailed risk management plan
Risk response plan
Risk mitigation plan
Change management process
How project RAID (Risk, Assumption, Issues, and Dependencies) will be managed
Stakeholder engagement – communication plan
Week 8 – Quality and Project Closure: At the end of week 8, you are to finalize the overall project management plan
(PMP). In this week, you are to integrate all previously submitted components incorporated with instructor (project
sponsor) feedback into a single project management plan. Project management plan will include the following comp
onents:
Project quality management plan to include an updated scope, cost, schedule, communication, risk, resources, procur
ement, and quality)
Updated changes – Change Request (if any)
Project requirements – updated
Stakeholder register – updated
How project RAID (Risk, Assumption, Issues, and Dependencies)
Document project lessons-learned
Project sponsor approval of the key project deliverables
For the project submission:
Students can use MS project (if they have access to it) or MS Excel, Word documents, and any other free related soft
ware they are able to access as long as they meet the assignment’s scoring rubrics/guidelines.
Project: scope of project
Date: 09/19/2021
Project Management-GE 5103
Cloud Migration (Private cloud to AWS)
Week4_Scope and Schedule
Finalized Scope:
The main purpose of this project is to transfer the data from one cloud to another of high availability and performance of project, so that we can secure the confidential files with access controls, the data storage, servers, network infrastructure, and security elements such as firewalls, setting up VPNs for project access everything can be done with in a data center, so far we do have 3 data centers as 2 for production and one for disaster recovery , so if any disaster occurs then the data can be recovered from disaster recovery center without any application delays.
Requirements:
Describe
Work Breakdown Structure:
You can use this for reference
Resource
Duration
Responsibility
Budget
Planned Start Date
Planned End Date
Project Manager
4mnths
Manage the project
$275
10/01/2021
01/31/2022
Software Engineer
4mnths
Develop the code and maintain
$250
10/01/2021
01/31/2022
Hardware Engineer
1mnth
Set up hardware
$125
01/01/2022
01/31/2022
Test Engineer
1mnth
1.Quality check of the product
2. Test if the product passes all safety and quality standard
$125
01/01/2022
01/31/2022
Logistic Manager
4mnths
Supply and maintain warehouse material during the project and procurement shipping
$700k
10/01/2022
01/01/2022
Develop Project Schedule:
Resource
Month1
Month2
Month3
Month4
Project Manager
Assigning all the task to the team
And kick off the project
Checking every 15days for progress
Review the progress made till date and add new features if required
Go through the project and identify if any missing features and deliver the product to clients.
Software Engineer
Develop the working simulation.
Run, test and complete the simulation HW and SW team to collaborate
Enhancements based on the hardware design; complete working s/w based on the working h/w
Fix the bugs identified by the QA and retest in lower environments and deliver error free software
Hardware Engineer
Develop the working simulation and decide on Hardware paths needed for the device
Runs, test and complete the simulation
Check for any updates required for the hardware and add additional capacity if required
Set up required hardware for final product and maintain.
Test Engineer
NA
Collects the list of supplies for procuring the hardware parts
Order and purchase the parts
Complete Regression, sandbox testing and write unit cases at each stage
Logistic Manager
NA
NA
Review the work made till date and give a sample demo to stake holders
Demo the final output and deliver to clients.
Key Milestones and Deliverables:
Identify key milestones in the project and explain why?
Hello Class- This is a very rough draft of the assignment. I have broken down each section and potential opportunities for you. This is not all inclusive as you can be creative but you must meet the deliverables of this assignment.
Scope and Schedule: At the end of week 4, you are to finalize the initially approved scope from week two and start building the project schedule. In this week, you are also to work on building the project Work-Breakdown Structure (WBS). Project scope and schedule will include the following components:
- Finalized project scope
- Project requirements – in more details
- WBS structure
- Developed project schedule
- Identify key milestones and deliverables
- Outline project resources and assign them to tasks accordingly.
- Stakeholder engagement – communication plan
Make sure that there is a heading for each section.
Title Page – Name, date, etc
· Finalized Project Scope: Chapter 7 Scope Planning,
I just want a summary of what your final scope is.
· Project Requirements – Details
· WBS Structure- (Week 3) Chapter 7 Video, How to construct a WBS?
·
· Developed Project Schedule – Chapter 8 Video – Develop Project Schedule, Chapter 8 Reading Scheduling Projects – May ways to show schedule just pick one.
Develop Project Schedule
Once you have an estimated duration for each activity in the network must determine (based on durations and sequence) whether the project can be realistically finished by the required completion time.
· In order to do this, the contractor should estimate the duration of each activity.
· He or she should establish an overall window of time for the project.
Develop a project schedule that provides a timetable for each activity and shows:
· The earliest times (or dates) at which each activity can start and finish, based on the project estimated start time (or date)
· The latest times (or dates) by which each activity must start and finish in order to complete the project by its required completion time (or date)
·
Incorporate Changes into Schedule
· Throughout a project, changes may occur that impact the schedule.
· Changes might be initiated by the customer or the project team, or they might be the result of an unanticipated occurrence.
· Changes requested early in the project may have less of an impact on schedule and budget than those requested later in the project.
· When the customer requests a change, the contractor or project team should estimate the impact on the project schedule and budget and then obtain customer approval before proceeding.
· If the customer approves the proposed revisions to the project schedule and budget, then any additional activities, revised estimated durations, and revised estimated resources and associated costs should be incorporated into the project schedule and budget.
· With respect to the project schedule, changes can result in the addition or deletion of activities, re-sequencing of activities, changes to estimated durations for specific activities, or a new required completion time for the project.
·
· Identify key milestones and deliverables – Write up your key or show them on your graph and point them out. Discuss in a summary what they are.
· Outline project resources and assign them to tasks accordingly
·
·
·
·
·
·
· Stakeholder engagement- communication plan
· 6-2aCreating a Stakeholder Engagement Assessment Matrix
· Project teams create a
stakeholder engagement plan
to define how they will effectively engage stakeholders in planning and performing the project based on the analysis of the stakeholders’ needs, wants, and impacts. A primary tool used in this plan is the
stakeholder engagement assessment matrix
. This matrix typically includes a first column showing the stakeholders. For each stakeholder, additional columns may represent how much they are currently supporting or opposing the project, where you would like them to be, barriers to their changing, and strategies you may employ to move them. Strategies for powerful and supporting stakeholders may include accepting their ideas, compromising, or offering them trade-offs, while strategies for opponents might entail doing the minimum possible or fighting their demnds. It is not uncommon to think that the best one can do with opposing stakeholders is to help move them to a neutral position, while those who are unaware of or neutral toward the project may be turned into supporters.
· Exhibit 6.5 identifies both the current and target positions of the stakeholder groups. The greater the change in position, the greater the risk and the greater the engagement effort required. Student Services had a relatively unimportant position in the old system but would be critical to the new modularized operation. Significant expenditure was anticipated in this area. It is of interest to note that the initial analysis (see
Exhibit 6.4
) had identified this group as “other stakeholder.” As the nature and impact of changes become clearer, they can alter the relative importance of different groups. Stakeholder positions and stakeholder strategies must be reevaluated throughout the project.
· Exhibit 6.5
· Modular Courses—Stakeholder Engagement Assessment Matrix
STAKEHOLDER
CURRENT POSITION
TARGET POSITION
BARRIERS TO CHANGE
STRATEGY
Vice Chancellor
Leading
Leading
Competing day-to-day priorities
Ensure engagement is ‘efficient’ and effective. Consider extending role of deputy Chancellor to cover for some day-to-day activities.
Deans of Faculty
Resistant
Neutral, Supportive, or Leading
Some Deans more powerful than others (relates to student numbers and academic ratings). ‘Power owners’ are very influential.
Consider each Dean’s WIIFT individually. Consider strategies for individuals as well as the group.
Academic Registrar (AR)
Supportive
Leading
Competing day-to-day priorities—lack of leadership skills.
Engage deputy, provide skills and mentorship.
Lecturers
Unaware to neutral
Neutral or supportive
Very large group with veto power through unionized actions.
Involve HR and legal department to evaluate
·
© 2018 Cengage®. May not be scanned, copied or duplicated, or posted to a publicly accessible website, in whole or in part, except for use as per mitted in a license distributed with a certain product or service or otherwise on a password -protected website or school -approved learning m anagement system for classroom use. IS Example: Resource Requirements
© 2018 Cengage®. May not be scanned, copied or duplicated, or posted to a publicly accessible website, in whole or in part, except for use as per mitted in a license distributed with a certain product or service or otherwise on a password -protected website or school -approved learning m anagement system for classroom use. IS Example: Responsibility Assignment Matrix
CATEGORIES
Economics
Nursing
Applied Sciences
Psychology
Science
Management
Computer Science
Human Resource Management
Accounting
Information Systems
English
Anatomy
Operations Management
Sociology
Literature
Education
Business & Finance
Marketing
Engineering
Statistics
Biology
Political Science
Reading
History
Financial markets
Philosophy
Mathematics
Law
Criminal
Architecture and Design
Government
Social Science
World history
Chemistry
Humanities
Business Finance
Writing
Programming
Telecommunications Engineering
Geography
Physics
Spanish
ach
e. Embedded Entrepreneurship
f. Three Social Entrepreneurship Models
g. Social-Founder Identity
h. Micros-enterprise Development
Outcomes
Subset 2. Indigenous Entrepreneurship Approaches (Outside of Canada)
a. Indigenous Australian Entrepreneurs Exami
Calculus
(people influence of
others) processes that you perceived occurs in this specific Institution Select one of the forms of stratification highlighted (focus on inter the intersectionalities
of these three) to reflect and analyze the potential ways these (
American history
Pharmacology
Ancient history
. Also
Numerical analysis
Environmental science
Electrical Engineering
Precalculus
Physiology
Civil Engineering
Electronic Engineering
ness Horizons
Algebra
Geology
Physical chemistry
nt
When considering both O
lassrooms
Civil
Probability
ions
Identify a specific consumer product that you or your family have used for quite some time. This might be a branded smartphone (if you have used several versions over the years)
or the court to consider in its deliberations. Locard’s exchange principle argues that during the commission of a crime
Chemical Engineering
Ecology
aragraphs (meaning 25 sentences or more). Your assignment may be more than 5 paragraphs but not less.
INSTRUCTIONS:
To access the FNU Online Library for journals and articles you can go the FNU library link here:
https://www.fnu.edu/library/
In order to
n that draws upon the theoretical reading to explain and contextualize the design choices. Be sure to directly quote or paraphrase the reading
ce to the vaccine. Your campaign must educate and inform the audience on the benefits but also create for safe and open dialogue. A key metric of your campaign will be the direct increase in numbers.
Key outcomes: The approach that you take must be clear
Mechanical Engineering
Organic chemistry
Geometry
nment
Topic
You will need to pick one topic for your project (5 pts)
Literature search
You will need to perform a literature search for your topic
Geophysics
you been involved with a company doing a redesign of business processes
Communication on Customer Relations. Discuss how two-way communication on social media channels impacts businesses both positively and negatively. Provide any personal examples from your experience
od pressure and hypertension via a community-wide intervention that targets the problem across the lifespan (i.e. includes all ages).
Develop a community-wide intervention to reduce elevated blood pressure and hypertension in the State of Alabama that in
in body of the report
Conclusions
References (8 References Minimum)
*** Words count = 2000 words.
*** In-Text Citations and References using Harvard style.
*** In Task section I’ve chose (Economic issues in overseas contracting)"
Electromagnetism
w or quality improvement; it was just all part of good nursing care. The goal for quality improvement is to monitor patient outcomes using statistics for comparison to standards of care for different diseases
e a 1 to 2 slide Microsoft PowerPoint presentation on the different models of case management. Include speaker notes... .....Describe three different models of case management.
visual representations of information. They can include numbers
SSAY
ame workbook for all 3 milestones. You do not need to download a new copy for Milestones 2 or 3. When you submit Milestone 3
pages):
Provide a description of an existing intervention in Canada
making the appropriate buying decisions in an ethical and professional manner.
Topic: Purchasing and Technology
You read about blockchain ledger technology. Now do some additional research out on the Internet and share your URL with the rest of the class
be aware of which features their competitors are opting to include so the product development teams can design similar or enhanced features to attract more of the market. The more unique
low (The Top Health Industry Trends to Watch in 2015) to assist you with this discussion.
https://youtu.be/fRym_jyuBc0
Next year the $2.8 trillion U.S. healthcare industry will finally begin to look and feel more like the rest of the business wo
evidence-based primary care curriculum. Throughout your nurse practitioner program
Vignette
Understanding Gender Fluidity
Providing Inclusive Quality Care
Affirming Clinical Encounters
Conclusion
References
Nurse Practitioner Knowledge
Mechanics
and word limit is unit as a guide only.
The assessment may be re-attempted on two further occasions (maximum three attempts in total). All assessments must be resubmitted 3 days within receiving your unsatisfactory grade. You must clearly indicate “Re-su
Trigonometry
Article writing
Other
5. June 29
After the components sending to the manufacturing house
1. In 1972 the Furman v. Georgia case resulted in a decision that would put action into motion. Furman was originally sentenced to death because of a murder he committed in Georgia but the court debated whether or not this was a violation of his 8th amend
One of the first conflicts that would need to be investigated would be whether the human service professional followed the responsibility to client ethical standard. While developing a relationship with client it is important to clarify that if danger or
Ethical behavior is a critical topic in the workplace because the impact of it can make or break a business
No matter which type of health care organization
With a direct sale
During the pandemic
Computers are being used to monitor the spread of outbreaks in different areas of the world and with this record
3. Furman v. Georgia is a U.S Supreme Court case that resolves around the Eighth Amendments ban on cruel and unsual punishment in death penalty cases. The Furman v. Georgia case was based on Furman being convicted of murder in Georgia. Furman was caught i
One major ethical conflict that may arise in my investigation is the Responsibility to Client in both Standard 3 and Standard 4 of the Ethical Standards for Human Service Professionals (2015). Making sure we do not disclose information without consent ev
4. Identify two examples of real world problems that you have observed in your personal
Summary & Evaluation: Reference & 188. Academic Search Ultimate
Ethics
We can mention at least one example of how the violation of ethical standards can be prevented. Many organizations promote ethical self-regulation by creating moral codes to help direct their business activities
*DDB is used for the first three years
For example
The inbound logistics for William Instrument refer to purchase components from various electronic firms. During the purchase process William need to consider the quality and price of the components. In this case
4. A U.S. Supreme Court case known as Furman v. Georgia (1972) is a landmark case that involved Eighth Amendment’s ban of unusual and cruel punishment in death penalty cases (Furman v. Georgia (1972)
With covid coming into place
In my opinion
with
Not necessarily all home buyers are the same! When you choose to work with we buy ugly houses Baltimore & nationwide USA
The ability to view ourselves from an unbiased perspective allows us to critically assess our personal strengths and weaknesses. This is an important step in the process of finding the right resources for our personal learning style. Ego and pride can be
· By Day 1 of this week
While you must form your answers to the questions below from our assigned reading material
CliftonLarsonAllen LLP (2013)
5 The family dynamic is awkward at first since the most outgoing and straight forward person in the family in Linda
Urien
The most important benefit of my statistical analysis would be the accuracy with which I interpret the data. The greatest obstacle
From a similar but larger point of view
4 In order to get the entire family to come back for another session I would suggest coming in on a day the restaurant is not open
When seeking to identify a patient’s health condition
After viewing the you tube videos on prayer
Your paper must be at least two pages in length (not counting the title and reference pages)
The word assimilate is negative to me. I believe everyone should learn about a country that they are going to live in. It doesnt mean that they have to believe that everything in America is better than where they came from. It means that they care enough
Data collection
Single Subject Chris is a social worker in a geriatric case management program located in a midsize Northeastern town. She has an MSW and is part of a team of case managers that likes to continuously improve on its practice. The team is currently using an
I would start off with Linda on repeating her options for the child and going over what she is feeling with each option. I would want to find out what she is afraid of. I would avoid asking her any “why” questions because I want her to be in the here an
Summarize the advantages and disadvantages of using an Internet site as means of collecting data for psychological research (Comp 2.1) 25.0\% Summarization of the advantages and disadvantages of using an Internet site as means of collecting data for psych
Identify the type of research used in a chosen study
Compose a 1
Optics
effect relationship becomes more difficult—as the researcher cannot enact total control of another person even in an experimental environment. Social workers serve clients in highly complex real-world environments. Clients often implement recommended inte
I think knowing more about you will allow you to be able to choose the right resources
Be 4 pages in length
soft MB-920 dumps review and documentation and high-quality listing pdf MB-920 braindumps also recommended and approved by Microsoft experts. The practical test
g
One thing you will need to do in college is learn how to find and use references. References support your ideas. College-level work must be supported by research. You are expected to do that for this paper. You will research
Elaborate on any potential confounds or ethical concerns while participating in the psychological study 20.0\% Elaboration on any potential confounds or ethical concerns while participating in the psychological study is missing. Elaboration on any potenti
3 The first thing I would do in the family’s first session is develop a genogram of the family to get an idea of all the individuals who play a major role in Linda’s life. After establishing where each member is in relation to the family
A Health in All Policies approach
Note: The requirements outlined below correspond to the grading criteria in the scoring guide. At a minimum
Chen
Read Connecting Communities and Complexity: A Case Study in Creating the Conditions for Transformational Change
Read Reflections on Cultural Humility
Read A Basic Guide to ABCD Community Organizing
Use the bolded black section and sub-section titles below to organize your paper. For each section
Losinski forwarded the article on a priority basis to Mary Scott
Losinksi wanted details on use of the ED at CGH. He asked the administrative resident