Group Research Project 2 - Management
This research project requires you to tie together the key components of project management.
Ensure all responses you provide (including numbers and facts) are supported with information from the journal, or where necessary, provide appropriate assumptions and additional information from external sources. However, facts from the journal will trump all external sources. This journal including all other external sources should be correctly referenced.
Use effective APA in-text citation to help the reader know exactly where you are picking your facts from.
Cleveland State University Cleveland State University 
[email protected] [email protected]
Civil and Environmental Engineering Faculty 
Publications Civil and Environmental Engineering 
6-2013 
1976 Montreal Olympics: Case Study of Project Management 1976 Montreal Olympics: Case Study of Project Management 
Failure Failure 
Ashish Patel 
HWH Architects Engineers Planners, Inc, [email protected]
Paul A. Bosela 
Cleveland State University, [email protected]
Norbert Delatte 
Cleveland State University, [email protected]
Follow this and additional works at: https://engagedscholarship.csuohio.edu/encee_facpub 
 Part of the Civil Engineering Commons, and the Construction Engineering and Management 
Commons 
How does access to this work benefit you? Let us know! How does access to this work benefit you? Let us know! 
Publishers Statement 
© ASCE 
Original Citation Original Citation 
Patel, A., Bosela, P., and Delatte, N. (2013). 1976 Montreal Olympics: Case Study of Project Management 
Failure. J.Perform.Constr.Facil., 27(3), 362-369. 
This Article is brought to you for free and open access by the Civil and Environmental Engineering at 
[email protected] It has been accepted for inclusion in Civil and Environmental Engineering Faculty 
Publications by an authorized administrator of [email protected] For more information, please contact 
[email protected] 
1976 Montreal Olympics: Case Study of Project 
Management Failure 
Ashish Patel1 ; Paul A. Bosela, F.ASCE2 ; and Norbert J. Delatte, F.ASCE3 
Introduction 
On May 12 . 1970 . ex tensive lobbyi ng and d ipl omacy by Montreal 
Mayor Jean Drapeau paid off when Montrea l was awarded the 1976 
O lympic Gam es over strong bids from Moscow and Los Angeles . 
Although both competing c ities provided fimmc iu l guarantees . 
Drapeau sialed thai the Games would cost il rnilximum of $ 124 
million and that the hi story and reputation of Montreal would stand 
in p lace of a guarantee (Auf deT Maur 1976). 
For the next fe w years, very little was done. The original plan was 
scrapped. Mayor Drapeau became enamored with architect Roger 
Taill ibert s Pare des Princcs in Paris. Tellingly, the construction cost fo r 
thai stadi um had ballooned from the original estimated $9 million to 
a final cost of $25 mi ll io n. Drnpeau se[ected Taillibert without a com
petition. Li ke T aillibert. Dmpeau had had previous problems with cost 
oveffilns. The Olympi c bid wa~ based in part on Montreal s successfu l 
hosting of the [967 Expo. However. the finul cost of the Expo was $430 
million- much more thoo the 1964 estimate of $ 160 million. A new 
plan was laid ou t in a press conference on April 6, 1972. Almost 2 years 
o f preparation time had been wa>ted (Auf der Maur (976). 
In November [972. Drapeau gave a fi g ure o f $3 10 mil lion a~ the 
tOia l projec ted cost of the Olympic Games. Of the $250 million in 
capita l e xpenditures in the budget, $130.8 million was for the sta
dium and $ 16.4 million fort he velodrome. The O lym pi c Village was 
listed undernoncapital expenditures as $5 mi llion. Howell teons th is 
Drapeau s kitc hen-tabl e budget that no one ever took serio us ly but 
that also no oneever gathered the data to challenge. It was suspiciou s 
from the stan , however, because the recenll y concluded Munic h 
Games had cost lh e equiv al en t of $600 million. Shortly afterward. 
in January 1973. Drapeau made hi s often-quoted (llIld often-derided) 
stat eme nt that the Monlreal Olympi cs ca n no more have a de fi ci t 
than a man cu n have a baby (Howel l 2009). Howell later observed 
that ··amazin g ly. evc ry tim e the Mayor rev ised hi s cost estimate. we 
believed thaI it was COITt!c t at last (Howe ll 2009). 
Drapeuu laid ou t u plan for $3 [0 million in financing. the bulk o f 
which wou ld come from the sa le of $250 million in Ol ympic com
memo mtive coin s. The fedeml government of Cooada reviewed th e 
budget and thought that $ [00 million in coi n s:tl es would be more 
rc;l listi c. The federal government d id nOI want to ge t stuck with the bill 
fo r the construction or th e Games. The c it y of Mon lrcuJ had mude Ihe 
commitmcnt. and Cooada und the Province of Quebec did not w ish to 
be responsible fo r fu lfi ll in g that commitment. Strangely. they seemed 
to think that the construction cosl estimates were in the ball park. At 
thi s point in the process. Drapeau sugge sted at 11 news conference that 
the real proble m wou ld be figuring out how to spend the surp lus from 
the fi rst self- financin g Gam es in O lympic hi story (Howell 2009). 
The extensive construction o f the Ol ympi c fac ilities was justi 
fied. in pan. on the idea that the facilit ie s co uld be used after the 
Games for other spons . speci fica ll y usin g the O lympic Stadium for 
the Montreal Expos baseball team. However. the potentia l users 
were not co nsulted during the pl:l11lling process (Howell 2009). T he 
suita bilit y of th e fu ci liti es for usc lifte r the Games ended will be 
di sc ussed later in th is paper 
James Neal begins hi s textbook. entit led COlI,rtm ctioll Cost Es-
lill!(IIillg COII epls and Their Appliw tiol1s (Neil 1979), with an 
eight-page case stud y of the Montrea l Olympi cs compl ex. Nick Auf 
der MaUL a newspaper columnist and me mber of the Montreal C ity 
Cou nc il. wrote The BiIlioll·Dollar Came: Jelln DrUpe(1II (m d the 
/976 Olympics about all the pro blems (Auf der Maur (976), 
In late July 1976, at the final session of the World Congress on 
Space Structures, a highly controversial panel discussion was held 
on the project, which was later documented in ASCE’s Civil En
gineering magazine. It included some prominent consulting engi
neers from the United States, such as Anton Tedesko and Lev Zetlin, 
and some engineers and architects from Canada and elsewhere. A 
sidebar to the article summarized some of the comments that had 
appeared in the Montreal Star newspaper under the title, “Cost-Be-
Damned Attitude Brought on Olympic Woes” (Civil Engineering 
1976). 
This paper has been assembled from a variety of sources rather 
than firsthand observations. As such, it could be subject to the biases 
of the authors of the source information and may be inadvertently 
slanted. Care has been taken to balance the opposing viewpoints as 
much as possible. 
Olympic Games, Politics, and Prestige 
The quadrennial Olympic Games are so prestigious that cities and 
countries commit substantial resources to bidding for the right to 
hold them and then invest heavily in the facilities in which to hold 
them. For the 1976 Games, Moscow and Los Angeles both bid 
against Montreal, and concerns about cold war politics weighted the 
scales in Montreal’s favor. Moscow would host the 1980 Games, 
boycotted by the United States and its allies, and Los Angeles would 
host the 1984 Games, boycotted by the Soviet Union and its allies, 
showing that the concerns about politics were well-founded. The 
Montreal Games also took place against the backdrop of the 1972 
Munich Games and the hostage crisis that resulted in the death of 
Israeli athletes. After 1972, there were concerns about how the 
Games could go on, if they should, and how they could be kept safe. 
Kidd (1992) contends that the politics of Canada, Quebec, and 
Montreal played a large part in the difficulties of the 1976 Games. 
Much of the tension was brought about by the resurgence of 
Quebec’s Francophone nationalism and the succession movement. 
In addition, Montreal had long been dominated economically, po
litically, and culturally by a small Anglophone elite that was at odds 
with the Quebec nationalism movement. The federal government of 
Canada supported Montreal’s bid reluctantly and ruled out direct 
financial support for the Games. Furthermore, Mayor Drapeau and 
Canadian Prime Minister Pierre Trudeau did not trust each other. As 
a result, it took a long time to set up the Olympic lottery and coin and 
stamp program to support the Games, which cost 34 months of lead 
time. The program was slowed by unpaid bills until the Province of 
Quebec reluctantly agreed to accept responsibility for any deficit in 
early 1973. 
The potential embarrassment of missing the opening of the 
Games provided a fixed construction deadline. The planning started 
about 2 years too late, and scheduling fell apart because it was phy
sically impossible to accommodate all the construction activities 
on the project site. The City of Montreal was too slow in preparing 
bid documents, so the work could not be competitively bid but 
was instead awarded to selected contractors. Double crews, double 
shifts, and overtime were used to attempt to increase productivity, 
but because of congestion, the increase in productivity was slight 
(Neil 1979). 
Political turmoil intervened during the Montreal Games. Canada 
refused to allow the Republic of China (Taiwan) to compete because 
Canada had recognized the People’s Republic of China in 1970, 
despite the fact that the Republic of China was a member of the 
International Olympic Committee (IOC). This caused considerable 
friction with the United States. A much larger issue came about 
involving New Zealand’s participation in the Games because the 
New Zealand rugby team had just played in South Africa, and South 
Africa was barred from the Olympics during the apartheid era. Just 
before the Montreal Olympics started, 28 African countries walked 
out of the Games, joined by Guyana and Iraq (Strenk 1978). 
The issues of the politics and prestige of the Olympic Games 
have continued since Montreal. “There’s a myth growing, on this 
Olympic mess, that it all started with the tacky, overcommercialized 
Summer Games in Atlanta. Which led to all the bribes and greed of 
Salt Lake City. It’s a nice myth, but it’s wrong. The real sleaze got its 
start with Jean Drapeau and the 1976 Olympic Games in Montreal. 
There was the blueprint for corruption.” (Fotheringham 1999, p. 76). 
Montreal Olympic Complex 
The Montreal Olympic complex consisted of a main stadium, a ve
lodrome (bicycle racing venue), roads, walkways, practice fields, an 
Olympic Village housing facility, and other structures and land
scaping. The complex is shown in Fig. 1. 
Planning began in 1970, and preliminary estimates prepared at 
that time indicated a projected cost for the entire complex of $120 
million, including a projected cost for the main stadium of $40 
million. The final cost in 1976 was $1.5 billion, with $836 million 
for the main stadium. In addition to the cost overruns, there were 
considerable time overruns, which meant that the complex was al
most not completed in time for the Olympics, and some of the final 
activities were still ongoing at the time the Olympics started. Major 
components originally planned, such as the retractable roof, were 
not begun until after the Olympics (Neil 1979). 
The original owner was the City of Montreal, Quebec, which 
contracted with architect Roger Taillibert to design the Olympic 
Park, including the Olympic Stadium and velodrome (Auf der Maur 
1976). Mr. Taillibert lived and conducted business in Paris, France. 
Both the velodrome and Olympic Stadium were relatively unusual, 
unique artistic creations. 
The Mayor of Montreal, Jean Drapeau, has been criticized for an 
almost worshipful attitude toward Taillibert. The mayor rejected 
cuts that could have saved up to $146 million. He insisted on 
building the stadium of concrete rather than steel because Taillibert 
was a precast-concrete expert—although a steel stadium might have 
cost $100 million less (Civil Engineering 1976). 
Taillabert, who was to be paid $10–15 million for his work, did 
not help public relations with his lack of modesty, saying “That’s all 
Fig. 1. Olympic Stadium complex during the 1976 Olympic Games 
(Parc Olympic Quebec 2011; credit: Olympic Park of Montréal) 
Canadians and North Americans talk about—money, money, 
money. It doesn’t interest me at all,” telling a reporter “Are you 
aware that the building of the stadium and velodrome constitutes 
a great moment in the history of architecture and technology?” (Civil 
Engineering 1976). 
Velodrome 
Prior to bidding for the Olympic Games, the City of Montreal had 
already committed to hosting the World Cycling Championships in 
the Olympic velodrome for the summer of 1974. Construction of 
the velodrome began in August 1973, a year in advance of the 
scheduled opening of the Championships on August 14, 1974. 
However, it turned out that the rocky subsoil was not solid enough 
to support the roof—a fact that had not been found by geologic 
soundings and subsurface tests. The location near the Saint Law
rence River, however, hinted at probable subsurface difficulties. The 
foundation problems, along with labor union conflicts, ensured that 
the velodrome could not open in time for the Championships. A 
temporary facility was quickly built at the University of Montréal 
football stadium. The makeshift site had an excellent view of 
Mount Royal and would have served very well for the Olympic 
Games, although the spectator capacity would have been less. The 
incident highlighted the problems with the Olympic construction, 
but by this time there were less than 2 years left to go (Howell 
2009). 
The contract for the velodrome construction was awarded to 
prime contractor Charles Duranceau with a $12 million bid, based 
on half-complete plans, in August 1973, and construction began 
later that year. It was the first and last contract of the Montreal 
Olympics issued through public bidding (Auf der Maur 1976). 
The velodrome consisted of three arches supported by abut
ments. It was designed to have the appearance of a cycling helmet, 
as shown in Fig. 2. The structure consisted almost entirely of arches 
171 m (560 ft) long and rising to 27 m (90 ft) high. The arches were 
made of precast-concrete sections positioned onto falsework on site 
and then posttensioned (D’Appolonia 1990). 
The horizontal component H of the arch thrust is given by 
qL2 
H ¼ ð1Þ 
8d 
where q 5 uniform load along the arch, L 5 span of the arch, and d 5 
height of the arch. For a given span L, as the depth decreases, the 
horizontal force increases. The low aspect ratio d/L of the arch, about 
1:6, produced very high horizontal thrust forces. 
The arch was supported by four abutments, designated W, X, Y, 
and Z in Fig. 3. Abutments X and Y were founded on good rock, but 
the rock was of questionable quality at Abutments W and Z. Addi
tional investigations showed that the rock was broken up to a depth 
of about 6 m (20 ft) and was over a thin layer of clay shale 150–600 
mm (6 in. to 2 ft) thick. The thin layer represented a potential slip 
surface for the abutments, and as a result, tendons had to be driven 
through that layer into competent rock (D’Appolonia 1990) (Fig. 4). 
Abutment Z, unlike the other three abutments, takes the combined 
thrust of three arches and, as a result, has to resist the highest forces. 
A critical construction operation was the decentering, or re
moval of the supporting falsework for the arches. The process 
would create the greatest loads on the abutments, about 32,000 tons 
on Abutment Z. A total of 36 jacks were used, each with a stroke 
of 25 mm (1 in.). Only 13 mm (0.5 in.) of displacement could be 
tolerated during decentering, and the operation was carefully mon
itored (D’Appolonia 1990). 
The soil problem of low bearing capacity and the high loads on 
the abutments had resulted in substantial time delays and cost 
overruns for the foundation work. Although the foundation of the 
velodrome had been estimated to cost $497,576, the final cost was 
$7,171, 876 because of the extensive grouting and anchorage system 
shown in Fig. 4. A large part of the construction delay was because 
the contractor had to wait on Taillibert to finish the plans. Once the 
final plans were received, it was necessary to develop construction 
plans for the falsework. The work quickly fell behind, and it was 
Fig. 2. Velodrome, now a biodome (Wikipedia Commons, http:// 
en.wikipedia.org/wiki/File:Biodome_Montreal.jpg, photograph by 
PtitLutin) 
Fig. 3. Plan and elevation of velodrome (1 ft 5 0:3 m)  
obvious that the 1974 date could not be met. More workers were 
hired, and extensive overtime was authorized, but the extra workers 
mostly got in each others’ way. By late fall 1974, $34 million had been 
spent on the velodrome, and it was not complete. New subcontractors 
were hired. Given the time constraints, most of the construction 
contracts were cost plus rather than low-bid fixed-cost contracts. 
There also were a number of labor problems, such as tasks taking 
too long, strikes, overtime, and extra equipment, which themselves 
added about $12 million to the project cost (Auf der Maur 1976). 
The final cost for the 7,000-seat velodrome was approximately 
$70 million, compared with a $60 million cost for a 60,000-seat 
domed stadium in Seattle, Washington, at the same time. The cost 
per seat was 10 times as high. There also remained the concern that 
acrylic panels in the roof posed a fire hazard (Auf der Maur 1976). 
Anton Tedesko was known for his efficient thin-concrete-shell 
structures, epitomized by the Hershey Arena that spanned 67 m 
(220 ft) with a shell only 89 mm (3.5 in.) thick (Billington and 
Billington 2006). He was strongly critical of the velodrome, stating 
that it should have had a greater construction depth (or height) that 
would have greatly reduced the forces. As Eq. (1) shows, H is in
versely proportional to d. It could also have been more structurally 
efficient if the dome and three-dimensional action had been con
sidered in the design. Tedesko stated that the structures “do damage 
to the cause of concrete. Our young people should be told that these 
structures did not have to be done this way. As built, this gigantic 
demonstration project is almost an argument against the use of con
crete and for the use of structural steel or aluminum under similar 
circumstances in the future” (Civil Engineering 1976, pp. 50–51). 
The velodrome was renovated starting in 1989 and transformed 
into a biodome managed by the City of Montreal in 1992. It is now 
part of the Montreal Nature Museum (Parc Olympique Quebec 2011). 
Olympic Stadium 
All the structures were dramatic, modern, and complex, none more 
so than the main stadium. The stadium may be seen in the upper 
Fig. 4. Typical arch abutment (Abutment Z) (1 ft 5 0:3 m)  
right of Fig. 1 and in its final configuration in Fig. 5. The stadium 
had a number of unusual features. It was intended to resemble an 
elliptical seashell with a handle, which would have a retractable 
fabric cover hanging from a tall mast over the opening. As Fig. 1 
shows, the mast and cover were not in place at the time of the Olympics 
(Neil 1979). They were added later and may be seen in Fig. 5. 
The general structural form appears to be a large elliptical dome 
with an opening in the middle for the fabric roof. If it were, in fact, 
a thin dome with a compression ring, it would be an efficient struc
tural form. However, it isn’t. The main structural members are com
plex precast concrete ribs, shown in Fig. 6. The ribs cantilever out 
over the stadium, and although the hollow ring inside the roof carries 
lighting and other support systems, it is not designed to carry com
pression forces. Because of the gentle slope of the roof, each pair 
of ribs is a different size. The ribs were glued and posttensioned. 
They proved to be very difficult to erect, so misalignments of the ribs 
were as much as 150 mm (6 in.). This was a problem because the 
posttensioning cables had to be threaded through tubes in the ring. 
During the winter, some empty posttensioning ducts became full of 
ice, and considerable time and expense were involved in removing 
Fig. 5. Olympic Stadium (Wikipedia Commons, http://en.wikipedia. 
org/wiki/File:Le_Stade_Olympique_3.jpg) 
Fig. 6. Ribs of the Olympic Stadium (Parc Olympic Quebec 2011; 
credit: Olympic Park of Montréal) 
the ice (Neil 1979). It has been estimated that if all the ribs had been 
the same size, $20–30 million could have been saved (Civil Engi
neering 1976). 
Furthermore, the stadium design did not consider construct-
ability and did not leave room for interior scaffolding. Many cranes 
were used instead, some holding ribs, and others holding workers, 
tools, and materials. Fig. 7 shows the congestion of cranes in the 
stadium. At one point, 80 cranes were used in the main stadium, and 
it was estimated that doubling the number of cranes only increased 
productivity 25\% because they could not work effectively given that 
they were in each other’s way (Neil 1979). 
“At one stage, there was a forest of 200 building cranes on the 
stadium site, some from as far as Calgary, while gravel truck drivers 
gleefully drove in, collected their fee, and then drove out the other 
end, unloaded, and just went around the block again. Skilled 
workers, at seven 10-hour shifts a week, pulled down $1,500 weekly 
by doing only 2 hours a day of actual work” (Fotheringham 1999, 
p. 76). 
Although epoxy-glued, posttensioned construction had been 
used successfully in Europe, it was new to the North American 
contractors. As with any new technology, there was a difficult 
learning process (Neil 1979). With the time constraints on this 
project, the use of an unfamiliar technique was not a good idea. 
Taillibert did not deliver the plans and specifications for the 
Olympic Stadium until the late summer of 1974. He had already 
gained a reputation for late delivery of construction documents. The 
contract to build the Olympic Stadium was awarded to Desourdy and 
Duranceau, as cost plus $9 million profit with a $1 million bonus if 
the site were ready on time. The contract was awarded without 
public tenders. It was a strange choice of contractor, given that 
Duranceau was already buried in difficulties with the velodrome. 
The Province of Quebec forced the hiring of Lalonde, Valois, 
Lamarre, Valois & Associates (known as Lalonde, Valois) as project 
manager over Drapeau’s resistance. The cost estimates of Lalonde, 
Valois proved to be no better than any of the others (Auf der Maur 
1976). 
At the beginning of 1975, the Olympic Organizing Committee 
(referred to as COJO from Comité de contrôle des Jeux olympiques) 
was very concerned about completion of the stadium and began to 
look for alternatives, such as finding or building a cheaper stadium 
nearby. Mayor Drapeau called an elaborate press conference to 
explain the cost projections and provide assurances that the stadium 
would be ready on time. He referred to a funding gap of $200 million, 
Fig. 7. Cranes at work in the Olympic Stadium (Parc Olympic Quebec 
2011; credit: Olympic Park of Montréal) 
refusing to call it a deficit. The alternate-stadium concept was 
scrapped (Auf der Maur 1976). 
Very generous terms were given to the precasters who built the 
concrete ribs, including a $230,000 rental of one plant for Olympic 
construction and a $500,000 extension built onto another plant with 
public funds, plus $685,000 in cash bonuses and honoraria. Pre-
casting costs rose from $16 million to $42 million (Auf der Maur 
1976). 
Late in the game, Taillibert insisted on adding a water cascade to 
the top of the parking garages connected to the stadium, adding at 
least $8 million to the cost. The parking garages, originally budgeted 
for an extravagant $25 million, cost $60 million, or about $13,000 
per parking space. The water cascade also would require 113 million 
L (30 million gal) of water (Auf der Maur 1976). 
Mayor Drapeau, with no engineering or architecture qualifica
tions, had spent much time poring over plans and going to the 
construction site to give orders, which confused the workers. Then, 
on December 13, 1974, Drapeau sent a representative to a meeting to 
say that the stadium construction would cost substantially more. The 
project continued to be troubled by labor demonstrations and strikes. 
Finally, on November 19, 1975, the Province of Quebec created the 
Régie des Installations Olympiques (RIO) to complete construction 
of the Olympic Park and take over as owner. Drapeau and Taillibert 
were now off the site. In assuming control from the City of Montreal, 
however, Quebec also assumed the expense (Howell 2009). 
Quebec advanced $200 million for the project but in return had to 
delay other important construction in Montreal, such as the subway 
and a sewage treatment plant. At that time, Montreal was one of the 
few cities in the Western world still dumping raw, untreated sewage 
into a river. Bills were paid, and construction continued, with no 
better cost control than before (Auf der Maur 1976). 
The final cost for the stadium was approximately $13,000 per 
seat, compared with approximately $2,400 per seat for the Super-
dome in New Orleans, Louisiana, constructed at approximately 
the same time (Neil 1979). The stadium was nicknamed the Big O 
because of its name and shape, but it later became known as the Big 
Owe (“Quebec’s” 2006). 
Tedesko and consulting engineer Lev Zetlin both criticized the 
stadium. Tedesko noted that anyone familiar with match-cast post-
tensioned precast-concrete construction would have predicted the 
difficulties encountered. Zetlin stated that a large-span structure 
should be light, permit a large margin of error in the field, and use 
construction methods that were as simple as possible, and the 
Montreal Olympic Stadium violated all these principles. He further 
criticized the heavy roof as a dead weight on top of the building 
(Civil Engineering 1976). 
After the 1976 Olympics, the Olympic Stadium saga continued. 
It was found that the tower could not be completed as planned in 
concrete without major structural work because it would be too 
heavy and that the tower would be overstressed by the Canadian 
standard (“Court” 1983). The tower was completed in steel and was 
damaged by a fire during construction (“Fire” 1986). The roof and 
tower were completed, but the retractable Kevlar roof was not in
stalled until 1986 and was stored in France and then Montreal at 
a cost of several million dollars. In 1989, the roof developed huge 
tears because of air pressure (“Experts” 1989). In 1991, a 55-t chunk 
of the roof fell after support beams snapped, forcing an extended 
closure. Fortunately, there were no injuries. All 33 beams had to be 
reinforced at a cost of several hundred thousand dollars. The failure 
may have been because of the use of an improper (e.g., not corrosion-
resistant) type of steel or poor welding (“55-ton” 1991; “Suspect” 
1991). Finally, RIO decided to replace the roof (“Fixing” 1993). The 
new roof tore again in the winter of 1999, forcing the cancellation of an 
auto show and a subsequent boat show (“Stadium” 1999). 
Olympic Village 
The Olympic Village project began in 1970, when at the presen
tations to win the Olympic bid in Amsterdam, Jean Drapeau an
nounced that the Olympic Village would be a low-rise structure 
that would be placed just to the east of the Olympic Stadium and 
Velodrome. The mayor said that the village would be used to pro
vide for 4,000 low-cost housing units after the Olympics were over, 
serving up to 14,000 tenants. The concept would fit in well for his 
self-financing Olympics because the Central Mortgage and Housing 
Commission (CMHC) would provide 95\% of the clearance cost and 
75\% of the construction cost (Auf der Maur 1976). 
There was a great debate on both where to place the Olympic 
Village and whether the village would be centralized or spread out. 
There were many protests against placing the complex in Viau Park 
because it would take away green space from a city that didn’t have 
much of it. However, at the end of 1972, Mayor Drapeau announced 
that the Olympic Village was going to be built in the park and that the 
village would be centralized, over all objections. The city also 
destroyed 125 elm trees on the site after promising not to remove 
any (Auf der Maur 1976). 
“In January 1974, a group from Montreal arrived in Baie des 
Anges, on the Côte d’Azur in southern France, the site of a spec
tacular pyramid-shaped condominium complex designed by archi
tect André Minangoy. The visitors, who included Montreal developer 
Joseph Zappia, told the sales director of the Baie des Anges project 
that they had been selected to build the Olympic Village for 1976. This 
was odd because the deadline for tenders was not until March 1, 
almost two months in the future” (Auf der Maur 1976). 
When the project went out to bid, 53 different groups or com
panies had paid the $100 to pick up the preliminary specifications 
and requirements. However, as the March 1 deadline came and went, 
the city announced that there were no suitable proposals and that the 
deadline was going to be postponed indefinitely. As time went on, 
many of the bidding companies never heard anything at all from the 
city …
				    	
					CATEGORIES
        	Economics 
        	Nursing 
        	Applied Sciences 
        	Psychology 
        	Science 
        	Management 
        	Computer Science 
        	Human Resource Management 
        	Accounting 
        	Information Systems 
        	English 
        	Anatomy 
        	Operations Management 
        	Sociology 
        	Literature 
        	Education 
        	Business & Finance 
        	Marketing 
        	Engineering 
        	Statistics  
        	Biology 
        	Political Science 
        	Reading 
        	History 
        	Financial markets 
        	Philosophy 
        	Mathematics 
        	Law 
        	Criminal 
        	Architecture and Design 
        	Government 
        	Social Science 
        	World history 
        	Chemistry 
        	Humanities
        	Business Finance
        	Writing
        	Programming
        	Telecommunications Engineering 
        	Geography 
        	Physics 
        	Spanish 
        	ach
e. Embedded Entrepreneurship
f. Three Social Entrepreneurship Models
g. Social-Founder Identity
h. Micros-enterprise Development
Outcomes
Subset 2. Indigenous Entrepreneurship Approaches (Outside of Canada)
a. Indigenous Australian Entrepreneurs Exami
        	Calculus 
        	(people influence of 
others) processes that you perceived occurs in this specific Institution Select one of the forms of stratification highlighted (focus on inter the intersectionalities 
of these three) to reflect and analyze the potential ways these (
        	American history 
        	Pharmacology 
        	Ancient history 
        	. Also
        	Numerical analysis 
        	Environmental science 
        	Electrical Engineering 
        	Precalculus 
        	Physiology 
        	Civil Engineering 
        	Electronic Engineering 
        	ness Horizons
        	Algebra 
        	Geology 
        	Physical chemistry 
        	nt
When considering both O
        	lassrooms
        	Civil 
        	Probability 
        	ions
Identify a specific consumer product that you or your family have used for quite some time. This might be a branded smartphone (if you have used several versions over the years)
        	or the court to consider in its deliberations. Locard’s exchange principle argues that during the commission of a crime
        	Chemical Engineering 
        	Ecology 
        	aragraphs (meaning 25 sentences or more). Your assignment may be more than 5 paragraphs but not less.
INSTRUCTIONS: 
To access the FNU Online Library for journals and articles you can go the FNU library link here: 
https://www.fnu.edu/library/
In order to
        	n that draws upon the theoretical reading to explain and contextualize the design choices. Be sure to directly quote or paraphrase the reading
        	ce to the vaccine. Your campaign must educate and inform the audience on the benefits but also create for safe and open dialogue. A key metric of your campaign will be the direct increase in numbers. 
Key outcomes: The approach that you take must be clear
        	Mechanical Engineering 
        	Organic chemistry 
        	Geometry 
        	nment 
Topic 
You will need to pick one topic for your project (5 pts) 
Literature search 
You will need to perform a literature search for your topic
        	Geophysics 
        	you been involved with a company doing a redesign of business processes
        	Communication on Customer Relations. Discuss how two-way communication on social media channels impacts businesses both positively and negatively. Provide any personal examples from your experience
        	od pressure and hypertension via a community-wide intervention that targets the problem across the lifespan (i.e. includes all ages).
Develop a community-wide intervention to reduce elevated blood pressure and hypertension in the State of Alabama that in
        	in body of the report
Conclusions
References (8 References Minimum)
*** Words count = 2000 words.
*** In-Text Citations and References using Harvard style.
*** In Task section I’ve chose (Economic issues in overseas contracting)"
        	Electromagnetism 
        	w or quality improvement; it was just all part of good nursing care.  The goal for quality improvement is to monitor patient outcomes using statistics for comparison to standards of care for different diseases
        	e a 1 to 2 slide Microsoft PowerPoint presentation on the different models of case management.  Include speaker notes... .....Describe three different models of case management.
        	visual representations of information. They can include numbers
        	SSAY
        	ame workbook for all 3 milestones. You do not need to download a new copy for Milestones 2 or 3. When you submit Milestone 3
        	pages):
Provide a description of an existing intervention in Canada
        	making the appropriate buying decisions in an ethical and professional manner.
Topic: Purchasing and Technology
You read about blockchain ledger technology. Now do some additional research out on the Internet and share your URL with the rest of the class 
        	be aware of which features their competitors are opting to include so the product development teams can design similar or enhanced features to attract more of the market. The more unique
        	low (The Top Health Industry Trends to Watch in 2015) to assist you with this discussion. 
  
    https://youtu.be/fRym_jyuBc0
Next year the $2.8 trillion U.S. healthcare industry will   finally begin to look and feel more like the rest of the business wo
        	evidence-based primary care curriculum. Throughout your nurse practitioner program
        	Vignette
Understanding Gender Fluidity
Providing Inclusive Quality Care
Affirming Clinical Encounters
Conclusion
References
Nurse Practitioner Knowledge
        	Mechanics 
        	and word limit is unit as a guide only.
The assessment may be re-attempted on two further occasions (maximum three attempts in total). All assessments must be resubmitted 3 days within receiving your unsatisfactory grade. You must clearly indicate “Re-su
        	Trigonometry 
        	Article writing
        	Other
        	5. June 29
        	After the components sending to the manufacturing house
        	1. In 1972 the Furman v. Georgia case resulted in a decision that would put action into motion. Furman was originally sentenced to death because of a murder he committed in Georgia but the court debated whether or not this was a violation of his 8th amend
        	One of the first conflicts that would need to be investigated would be whether the human service professional followed the responsibility to client ethical standard.  While developing a relationship with client it is important to clarify that if danger or
        	Ethical behavior is a critical topic in the workplace because the impact of it can make or break a business
        	No matter which type of health care organization
        	With a direct sale
        	During the pandemic
        	Computers are being used to monitor the spread of outbreaks in different areas of the world and with this record
        	3. Furman v. Georgia is a U.S Supreme Court case that resolves around the Eighth Amendments ban on cruel and unsual punishment in death penalty cases. The Furman v. Georgia case was based on Furman being convicted of murder in Georgia. Furman was caught i
        	One major ethical conflict that may arise in my investigation is the Responsibility to Client in both Standard 3 and Standard 4 of the Ethical Standards for Human Service Professionals (2015).  Making sure we do not disclose information without consent ev
        	4. Identify two examples of real world problems that you have observed in your personal
        	Summary & Evaluation: Reference & 188. Academic Search Ultimate
        	Ethics
        	We can mention at least one example of how the violation of ethical standards can be prevented. Many organizations promote ethical self-regulation by creating moral codes to help direct their business activities
        	*DDB is used for the first three years
        	For example
        	The inbound logistics for William Instrument refer to purchase components from various electronic firms. During the purchase process William need to consider the quality and price of the components. In this case
        	4. A U.S. Supreme Court case known as Furman v. Georgia (1972) is a landmark case that involved Eighth Amendment’s ban of unusual and cruel punishment in death penalty cases (Furman v. Georgia (1972)
        	With covid coming into place
        	In my opinion
        	with
        	Not necessarily all home buyers are the same! When you choose to work with we buy ugly houses Baltimore & nationwide USA
        	The ability to view ourselves from an unbiased perspective allows us to critically assess our personal strengths and weaknesses. This is an important step in the process of finding the right resources for our personal learning style. Ego and pride can be 
        	· By Day 1 of this week
        	While you must form your answers to the questions below from our assigned reading material
        	CliftonLarsonAllen LLP (2013)
        	5 The family dynamic is awkward at first since the most outgoing and straight forward person in the family in Linda
        	Urien
        	The most important benefit of my statistical analysis would be the accuracy with which I interpret the data. The greatest obstacle
        	From a similar but larger point of view
        	4 In order to get the entire family to come back for another session I would suggest coming in on a day the restaurant is not open
        	When seeking to identify a patient’s health condition
        	After viewing the you tube videos on prayer
        	Your paper must be at least two pages in length (not counting the title and reference pages)
        	The word assimilate is negative to me. I believe everyone should learn about a country that they are going to live in. It doesnt mean that they have to believe that everything in America is better than where they came from. It means that they care enough 
        	Data collection
        	Single Subject Chris is a social worker in a geriatric case management program located in a midsize Northeastern town. She has an MSW and is part of a team of case managers that likes to continuously improve on its practice. The team is currently using an
        	I would start off with Linda on repeating her options for the child and going over what she is feeling with each option.  I would want to find out what she is afraid of.  I would avoid asking her any “why” questions because I want her to be in the here an
        	Summarize the advantages and disadvantages of using an Internet site as means of collecting data for psychological research (Comp 2.1) 25.0\% Summarization of the advantages and disadvantages of using an Internet site as means of collecting data for psych
        	Identify the type of research used in a chosen study
        	Compose a 1
        	Optics
        	effect relationship becomes more difficult—as the researcher cannot enact total control of another person even in an experimental environment. Social workers serve clients in highly complex real-world environments. Clients often implement recommended inte
        	I think knowing more about you will allow you to be able to choose the right resources
        	Be 4 pages in length
        	soft MB-920 dumps review and documentation and high-quality listing pdf MB-920 braindumps also recommended and approved by Microsoft experts. The practical test
        	g
        	One thing you will need to do in college is learn how to find and use references. References support your ideas. College-level work must be supported by research. You are expected to do that for this paper. You will research
        	Elaborate on any potential confounds or ethical concerns while participating in the psychological study 20.0\% Elaboration on any potential confounds or ethical concerns while participating in the psychological study is missing. Elaboration on any potenti
        	3 The first thing I would do in the family’s first session is develop a genogram of the family to get an idea of all the individuals who play a major role in Linda’s life. After establishing where each member is in relation to the family
        	A Health in All Policies approach
        	Note: The requirements outlined below correspond to the grading criteria in the scoring guide. At a minimum
        	Chen
        	Read Connecting Communities and Complexity: A Case Study in Creating the Conditions for Transformational Change
        	Read Reflections on Cultural Humility
        	Read A Basic Guide to ABCD Community Organizing
        	Use the bolded black section and sub-section titles below to organize your paper.  For each section
        	Losinski forwarded the article on a priority basis to Mary Scott
        	Losinksi wanted details on use of the ED at CGH. He asked the administrative resident