Project Management: The Managerial Process 7th Edition (May 2017) By Larson and Gray. • Please answer part 1, 2, 3, 4, 5, and 6 of the Conveyor Belt Project - Operations Management
the answer of the below question in MS format
· Project Management: The Managerial Process 7th Edition (May 2017) By Larson and Gray.
· Please answer part 1, 2, 3, 4, 5, and 6 of the Conveyor Belt Project
626 Appendix 2 Computer Project Exercises
Part B
You have told Robin Lane that based on what you know now you need to revise the
estimates for some of the remaining activities. Detailed Product Design is expected to
take 3 days longer than planned. Build Prototypes is expected to take 2 days less than
planned and Finalized Product Design is expected to take 3 days longer than planned.
Final Manufacturing Process is expected to take 2 days less than planned, while Install
Production Equipment is now expected to take only 30 days. You also report that
Detailed Marketing plan will be completed before the end of the New Year. She is
insisting that the project be completed by January 17th in order to be ready for the Las
Vegas show. She is willing to spend $50,000 from Management Reserves to expedite
shipping if necessary. $25,000 would reduce the shipping of components by 5 days
and/or $25,000 would reduce the shipping of manufacturing parts by 5 days (Hint:
Adjust lag). Prepare a memo to Robin that addresses the following questions:
1. What is the impact of the revised estimates for Finalized Product Design and Install
Production Equipment on the project schedule and cost?
2. Would you recommend authorizing the expenditure of $50,000? Explain.
3. What, if any other recommendations, would you make so that the project can
achieve Robin’s deadline? Justify your recommendations.
Include a Tracking Gantt chart with variance schedule that depicts your final recom-
mendations and revised schedule.
Hint: After adjusting the Installation of Production Equipment and Finalized Product
Design, level outside of slack to eliminate any resource over allocation problems.
Conveyor Belt Project
Part 1
Project Description
The new computer-controlled conveyor belt is an exciting project that moves and positions
items on the conveyor belt within <1 millimeter. The project will produce a new system for
future installations, and for replacement of those in the field, at a low cost. The computer-
controlled conveyor belt has the potential to be a critical unit in 30 percent of the systems
installed in factories. The new system is also easier to update with future technologies.
The Project Priority Matrix for the Conveyor Belt Project (CBP) is:
Time Scope Cost
Constrain X
Enhance X
Accept X
Table A2.9 has been developed for you to use in completing the project exercises.
Assignment
Develop the WBS outline using the software available to you.
Question
Does this information (WBS) allow you to define any milestones of the project? Why
or why not? What are they?
Remember: Save your file for future exercises!
Appendix 2 Computer Project Exercises 627
TABLE A2.9
Conveyor Belt
Project; WBS
Conveyor Belt Project
Hardware Hardware specifications
Hardware design
Hardware documentation
Prototypes
Order circuit boards
Assemble preproduction models
Operating system Kernel specifications
Drivers
Disk drivers
Serial I/O drivers
Memory management
Operating system documentation
Network interface
Utilities Utilities specifications
Routine utilities
Complex utilities
Utilities documentation
Shell
System integration Architectural decisions
Integration first phase
System hard/software test
Project documentation
Integration acceptance testing
Part 2
Use your file from Part 1 and the information provided below to complete this
exercise. (See Table A2.10.)
1. Each work package will represent an activity.
2. The project begins January 4, 2010.
3. The following holidays are observed: January 1, Memorial Day (last Monday in
May), July 4th, Labor Day (first Monday in September), Thanksgiving Day (4th
Thursday in November), December 25 and 26.
4. If a holiday falls on a Saturday then Friday will be given as an extra day off, and if
it falls on a Sunday, then Monday will be given as a day off.
5. The project teams work eight-hour days, Monday through Friday.
Warning: Experience has taught students to frequently make separate backup files for
each exercise. The software is never as friendly as users expect!
Construct a network schedule for the conveyor belt project and prepare a memo that
addresses the following questions:
1. When is the project estimated to be completed? How long will the project take?
2. What is the critical path(s) for the project?
3. Which activity has the greatest amount of slack?
4. How sensitive is this network?
5. Identify two sensible milestones and explain your choices.
6. Compare the advantages/disadvantages of displaying the schedule as a network
versus a Gantt chart.
www.ebook3000.com
http://www.ebook3000.org
628 Appendix 2 Computer Project Exercises
Include the following printouts:
∙ A Gantt chart.
∙ A network diagram highlighting the critical path.
∙ A schedule table reporting ES, LS, EF, LF, and slack for each activity.
Hint: the project should be completed in 530 days.
Remember: Save your file for future exercises!
Part 3
Remember the old saying, “A project plan is not a schedule until resources are com-
mitted.” This exercise illustrates this subtle, but very important, difference.
Part A
Using your files from Part 2 input resources and their costs if you have not already
done so. All information is found in Tables A2.10 and A2.11.
TABLE A2.10 Conveyor Belt Project; Schedule
Activity Description Resource Duration (days) Preceding Activity
1 Architectural decisions Design 25 —
2 Hardware specifications Development, design 50 1
3 Kernel specifications Design 20 1
4 Utilities specifications Development, design 15 1
5 Hardware design Design, development 70 2
6 Disk drivers Assembly, development 100 3
7 Memory management Development 90 3
8 Operating system documentation Design, documentation 25 3
9 Routine utilities Development 60 4
10 Complex utilities Development 80 4
11 Utilities documentation Documentation, design 20 4
12 Hardware documentation Documentation, design 30 5
13 Integration first phase Assembly, development 50 6,7,8,9,10,11,12
14 Prototypes Assembly, development 80 13
15 Serial I/O drivers Development 130 13
16 System hard/software test Assembly 25 14,15
17 Order circuit boards Purchasing 5 16
18 Network interface Development 90 16
19 Shell Development 60 16
20 Project documentation Documentation, development 50 16
21 Assemble preproduction models Assembly, development 30 17F-S, lag 50 days
22 Integrated acceptance testing Assembly, development 60 18,19,20,21
Note: F-S refers to a Finish-to-Start lag.
TABLE A2.11
Organization
Resources
Name Group Cost ($/hr)
Design R&D (2 teams) $100
Development R&D (2 teams) 70
Documentation R&D (1 team) 60
Assembly/test R&D (1 team) 70
Purchasing Procurement (1 team) 40
Appendix 2 Computer Project Exercises 629
Prepare a memo that addresses the following questions:
1. Which if any of the resources are overallocated?
2. Assume that the project is time constrained and try to resolve any overallocation
problems by leveling within slack. What happens?
3. What is the impact of leveling within slack on the sensitivity of the network?
Include a Gantt chart with the schedule table after leveling within slack.
4. Assume the project is resource constrained and resolve any overallocation
problems by leveling outside of slack. What happens? What are the managerial
implications?
5. What options are available at this point in time?
Include a Gantt chart with the schedule table after leveling outside of slack.
Note: No splitting of activities is allowed.
Note: No partial assignments (e.g., 50 percent). All resources must be assigned 100
percent.
Part B
When you show the resource-constrained network to top management, they are visibly
shaken. After some explanation and negotiation they make the following compromise
with you:
∙ The project must be completed no later than February 2, 2012 (530 days).
∙ You may assign two additional development teams.
∙ If this does not suffice, you may hire other development teams from the outside.
Hire as few external teams as possible because they cost $50 more per hour than
your inside development people.
Internal Development
Add as many development units (teams) as needed to stay within the 530 days. If you
need more than two internal development units, then hire as few external teams as
necessary. Select the cheapest possibility! Change as few activities as possible. It is
recommended you keep work packages which require cooperation of several organiza-
tional units inside your company. You decide how best to do this.
Hint: Undo leveling prior to adding new resources.
Once you have obtained a schedule that meets the time and resource constraints,
prepare a memo that addresses the following questions:
1. What changes did you make and why?
2. How long will the project take?
3. How did these changes affect the sensitivity of the network?
Include a Gantt chart with a schedule table presenting the new schedule.
www.ebook3000.com
http://www.ebook3000.org
630 Appendix 2 Computer Project Exercises
Part 4
Based on the file created at the end of Part 3, prepare a memo that addresses the fol-
lowing questions:
1. How much will the project cost?
2. What does the cash flow statement tell you about how costs are distributed over the
life span of the project?
Include a monthly cash flow and a cost table for the project.
Once you are confident that you have the final schedule, save the file as a
baseline.
Hint: Save a backup file just in case without baseline!
Part 5
Prepare status reports for each of the first four quarters of the project given the infor-
mation provided here. This requires saving your resource schedule as a baseline and
inserting the appropriate status report date in the program. Assume that no work has
been completed on the day of the status report.
Your status report should include a table containing the PV, EV, AC, BAC, EAC,
SV, CV, and CPI for each activity and the whole project. The report should also address
the following questions:
1. How is the project progressing in terms of cost and schedule?
2. What activities have gone well? What activities have not gone well?
3. What do the PCIB and PCIC indicate in terms of how much of the project has been
accomplished to date?
4. What is the forecasted cost at completion (EACf)? What is the predicted VACf?
5. Report and interpret the TCPI for the project at this point in time.
6. What is the estimated date of completion?
7. How well is the project doing in terms of its priorities?
Try to present the above information in a form worthy of consideration by top
management.
Include a Tracking Gantt chart with each report.
First Quarter, April 1, 2010
Table A2.12 summarizes the information regarding activities accomplished to date.
Be sure to save your file after each quarterly report and use it to build the next report!
Actual Remaining
Activity Start Date Finish Date Duration Duration
Hardware specifications 2/9/10 37 8
Kernel specifications 2/8/10 3/12/10 25 0
Disk drivers 3/15/10 13 87
Memory management 3/15/10 13 77
Op. systems documentation 3/15/10 13 7
Utilities specifications 3/8/10 3/29/10 16 0
Complex utilities 3/30/10 2 85
Architectural decisions 1/4/10 2/5/10 25 0
TABLE A2.12
April 1, 2010
Appendix 2 Computer Project Exercises 631
Second Quarter, July 1, 2010
Table A2.13 summarizes the information regarding activities accomplished since the
last report.
Third Quarter, October 1, 2010
Table A2.14 summarizes the information regarding activities accomplished since the
last report.
Fourth Quarter, January 1, 2011
Table A2.15 summarizes the information regarding activities accomplished since the
last report.
Part 6
You have received revised estimates for the remaining activities at the end of the fourth
quarter:
∙ Prototypes will be completed on 3/8/11.
∙ Serial I/O drivers will be completed on 6/30/11.
Actual Remaining
Activity Start Date Finish Date Duration Duration
Hardware specifications 2/9/10 4/12/10 45 0
Hardware design 4/13/10 56 11
Kernel specifications 2/8/10 3/12/10 25 0
Disk drivers 3/15/10 77 33
Memory management 3/15/10 77 19
Op. systems documentation 3/15/10 4/16/10 25 0
Utilities specifications 3/8/10 3/29/10 16 0
Routine utilities* 4/26/10 47 18
Complex utilities 3/30/10 66 25
Utilities documentation 5/3/10 6/2/10 22 0
Architectural decisions 1/4/10 2/5/10 25 0
TABLE A2.13
July 1, 2010
* The project manager for the external development team that was hired to perform routine utilities reported that due to commitments to
other clients they would be able to start on that activity 4/26/10.
Actual Remaining
Activity Start Date Finish Date Duration Duration
Hardware specifications 2/9/10 4/12/10 45 0
Hardware design 4/13/10 7/16/10 67 0
Hardware documentation 7/19/10 8/24/10 27 0
Kernel specifications 2/8/10 3/12/10 25 0
Disk drivers 3/15/10 8/17/10 110 0
Memory management 3/15/10 7/30/10 98 0
Op. systems documentation 3/15/10 4/16/10 25 0
Utilities specifications 3/8/10 3/29/10 16 0
Routine utilities 4/26/10 7/27/10 65 0
Complex utilities 3/30/10 8/11/10 95 0
Utilities documentation 5/3/10 6/2/10 22 0
Architectural decisions 1/4/10 2/5/10 25 0
Integration 1st phase 8/25/10 26 24
TABLE A2.14
October 1, 2010
www.ebook3000.com
http://www.ebook3000.org
632 Appendix 2 Computer Project Exercises
∙ System hardware/software test will start on 7/1/11 and take 25 days.
∙ Order circuit boards will start on 8/8/11 and take 5 days.
∙ Assemble preproduction model will begin on 10/14/11 and take 18 days.
∙ Project documentation is expected to start on 8/8/11 and will take 55 days.
∙ Network interface is expected to start on 8/8/11 and will take 99 days.
∙ Shell is expected to start on 8/8/11 and will take 55 days.
∙ Integrated acceptance testing is expected to start on 12/29/11 and will take 54 days.
Prepare a memo that addresses the following questions:
1. What is the new EAC for the project? How long should the project take given these
revised estimates?
2. How happy will top management be with these forecasts given the priorities of the
project?
3. What recommendations would you make?
Include a revised schedule, a Tracking Gantt chart, and cost table with your memo.
Actual Remaining
Activity Start Date Finish Date Duration Duration
Hardware specifications 2/9/10 4/12/10 45 0
Hardware design 4/13/10 7/16/10 67 0
Hardware documentation 7/19/10 8/24/10 27 0
Prototypes 11/11/10 34 44
Kernel specifications 2/8/10 3/12/10 25 0
Disk drivers 3/15/10 8/17/10 110 0
Serial I/O drivers 11/11/10 34 119
Memory management 3/15/10 7/30/10 98 0
Op. systems documentation 3/15/10 4/16/10 25 0
Utilities specifications 3/8/10 3/29/10 16 0
Routine utilities 4/26/10 7/27/10 65 0
Complex utilities 3/30/10 8/11/10 95 0
Utilities documentation 5/3/10 6/2/10 22 0
Architectural decisions 1/4/10 2/5/10 25 0
Integration 1st phase 8/25/10 11/10/10 55 0
TABLE A2.15
January 1, 2011
CATEGORIES
Economics
Nursing
Applied Sciences
Psychology
Science
Management
Computer Science
Human Resource Management
Accounting
Information Systems
English
Anatomy
Operations Management
Sociology
Literature
Education
Business & Finance
Marketing
Engineering
Statistics
Biology
Political Science
Reading
History
Financial markets
Philosophy
Mathematics
Law
Criminal
Architecture and Design
Government
Social Science
World history
Chemistry
Humanities
Business Finance
Writing
Programming
Telecommunications Engineering
Geography
Physics
Spanish
ach
e. Embedded Entrepreneurship
f. Three Social Entrepreneurship Models
g. Social-Founder Identity
h. Micros-enterprise Development
Outcomes
Subset 2. Indigenous Entrepreneurship Approaches (Outside of Canada)
a. Indigenous Australian Entrepreneurs Exami
Calculus
(people influence of
others) processes that you perceived occurs in this specific Institution Select one of the forms of stratification highlighted (focus on inter the intersectionalities
of these three) to reflect and analyze the potential ways these (
American history
Pharmacology
Ancient history
. Also
Numerical analysis
Environmental science
Electrical Engineering
Precalculus
Physiology
Civil Engineering
Electronic Engineering
ness Horizons
Algebra
Geology
Physical chemistry
nt
When considering both O
lassrooms
Civil
Probability
ions
Identify a specific consumer product that you or your family have used for quite some time. This might be a branded smartphone (if you have used several versions over the years)
or the court to consider in its deliberations. Locard’s exchange principle argues that during the commission of a crime
Chemical Engineering
Ecology
aragraphs (meaning 25 sentences or more). Your assignment may be more than 5 paragraphs but not less.
INSTRUCTIONS:
To access the FNU Online Library for journals and articles you can go the FNU library link here:
https://www.fnu.edu/library/
In order to
n that draws upon the theoretical reading to explain and contextualize the design choices. Be sure to directly quote or paraphrase the reading
ce to the vaccine. Your campaign must educate and inform the audience on the benefits but also create for safe and open dialogue. A key metric of your campaign will be the direct increase in numbers.
Key outcomes: The approach that you take must be clear
Mechanical Engineering
Organic chemistry
Geometry
nment
Topic
You will need to pick one topic for your project (5 pts)
Literature search
You will need to perform a literature search for your topic
Geophysics
you been involved with a company doing a redesign of business processes
Communication on Customer Relations. Discuss how two-way communication on social media channels impacts businesses both positively and negatively. Provide any personal examples from your experience
od pressure and hypertension via a community-wide intervention that targets the problem across the lifespan (i.e. includes all ages).
Develop a community-wide intervention to reduce elevated blood pressure and hypertension in the State of Alabama that in
in body of the report
Conclusions
References (8 References Minimum)
*** Words count = 2000 words.
*** In-Text Citations and References using Harvard style.
*** In Task section I’ve chose (Economic issues in overseas contracting)"
Electromagnetism
w or quality improvement; it was just all part of good nursing care. The goal for quality improvement is to monitor patient outcomes using statistics for comparison to standards of care for different diseases
e a 1 to 2 slide Microsoft PowerPoint presentation on the different models of case management. Include speaker notes... .....Describe three different models of case management.
visual representations of information. They can include numbers
SSAY
ame workbook for all 3 milestones. You do not need to download a new copy for Milestones 2 or 3. When you submit Milestone 3
pages):
Provide a description of an existing intervention in Canada
making the appropriate buying decisions in an ethical and professional manner.
Topic: Purchasing and Technology
You read about blockchain ledger technology. Now do some additional research out on the Internet and share your URL with the rest of the class
be aware of which features their competitors are opting to include so the product development teams can design similar or enhanced features to attract more of the market. The more unique
low (The Top Health Industry Trends to Watch in 2015) to assist you with this discussion.
https://youtu.be/fRym_jyuBc0
Next year the $2.8 trillion U.S. healthcare industry will finally begin to look and feel more like the rest of the business wo
evidence-based primary care curriculum. Throughout your nurse practitioner program
Vignette
Understanding Gender Fluidity
Providing Inclusive Quality Care
Affirming Clinical Encounters
Conclusion
References
Nurse Practitioner Knowledge
Mechanics
and word limit is unit as a guide only.
The assessment may be re-attempted on two further occasions (maximum three attempts in total). All assessments must be resubmitted 3 days within receiving your unsatisfactory grade. You must clearly indicate “Re-su
Trigonometry
Article writing
Other
5. June 29
After the components sending to the manufacturing house
1. In 1972 the Furman v. Georgia case resulted in a decision that would put action into motion. Furman was originally sentenced to death because of a murder he committed in Georgia but the court debated whether or not this was a violation of his 8th amend
One of the first conflicts that would need to be investigated would be whether the human service professional followed the responsibility to client ethical standard. While developing a relationship with client it is important to clarify that if danger or
Ethical behavior is a critical topic in the workplace because the impact of it can make or break a business
No matter which type of health care organization
With a direct sale
During the pandemic
Computers are being used to monitor the spread of outbreaks in different areas of the world and with this record
3. Furman v. Georgia is a U.S Supreme Court case that resolves around the Eighth Amendments ban on cruel and unsual punishment in death penalty cases. The Furman v. Georgia case was based on Furman being convicted of murder in Georgia. Furman was caught i
One major ethical conflict that may arise in my investigation is the Responsibility to Client in both Standard 3 and Standard 4 of the Ethical Standards for Human Service Professionals (2015). Making sure we do not disclose information without consent ev
4. Identify two examples of real world problems that you have observed in your personal
Summary & Evaluation: Reference & 188. Academic Search Ultimate
Ethics
We can mention at least one example of how the violation of ethical standards can be prevented. Many organizations promote ethical self-regulation by creating moral codes to help direct their business activities
*DDB is used for the first three years
For example
The inbound logistics for William Instrument refer to purchase components from various electronic firms. During the purchase process William need to consider the quality and price of the components. In this case
4. A U.S. Supreme Court case known as Furman v. Georgia (1972) is a landmark case that involved Eighth Amendment’s ban of unusual and cruel punishment in death penalty cases (Furman v. Georgia (1972)
With covid coming into place
In my opinion
with
Not necessarily all home buyers are the same! When you choose to work with we buy ugly houses Baltimore & nationwide USA
The ability to view ourselves from an unbiased perspective allows us to critically assess our personal strengths and weaknesses. This is an important step in the process of finding the right resources for our personal learning style. Ego and pride can be
· By Day 1 of this week
While you must form your answers to the questions below from our assigned reading material
CliftonLarsonAllen LLP (2013)
5 The family dynamic is awkward at first since the most outgoing and straight forward person in the family in Linda
Urien
The most important benefit of my statistical analysis would be the accuracy with which I interpret the data. The greatest obstacle
From a similar but larger point of view
4 In order to get the entire family to come back for another session I would suggest coming in on a day the restaurant is not open
When seeking to identify a patient’s health condition
After viewing the you tube videos on prayer
Your paper must be at least two pages in length (not counting the title and reference pages)
The word assimilate is negative to me. I believe everyone should learn about a country that they are going to live in. It doesnt mean that they have to believe that everything in America is better than where they came from. It means that they care enough
Data collection
Single Subject Chris is a social worker in a geriatric case management program located in a midsize Northeastern town. She has an MSW and is part of a team of case managers that likes to continuously improve on its practice. The team is currently using an
I would start off with Linda on repeating her options for the child and going over what she is feeling with each option. I would want to find out what she is afraid of. I would avoid asking her any “why” questions because I want her to be in the here an
Summarize the advantages and disadvantages of using an Internet site as means of collecting data for psychological research (Comp 2.1) 25.0\% Summarization of the advantages and disadvantages of using an Internet site as means of collecting data for psych
Identify the type of research used in a chosen study
Compose a 1
Optics
effect relationship becomes more difficult—as the researcher cannot enact total control of another person even in an experimental environment. Social workers serve clients in highly complex real-world environments. Clients often implement recommended inte
I think knowing more about you will allow you to be able to choose the right resources
Be 4 pages in length
soft MB-920 dumps review and documentation and high-quality listing pdf MB-920 braindumps also recommended and approved by Microsoft experts. The practical test
g
One thing you will need to do in college is learn how to find and use references. References support your ideas. College-level work must be supported by research. You are expected to do that for this paper. You will research
Elaborate on any potential confounds or ethical concerns while participating in the psychological study 20.0\% Elaboration on any potential confounds or ethical concerns while participating in the psychological study is missing. Elaboration on any potenti
3 The first thing I would do in the family’s first session is develop a genogram of the family to get an idea of all the individuals who play a major role in Linda’s life. After establishing where each member is in relation to the family
A Health in All Policies approach
Note: The requirements outlined below correspond to the grading criteria in the scoring guide. At a minimum
Chen
Read Connecting Communities and Complexity: A Case Study in Creating the Conditions for Transformational Change
Read Reflections on Cultural Humility
Read A Basic Guide to ABCD Community Organizing
Use the bolded black section and sub-section titles below to organize your paper. For each section
Losinski forwarded the article on a priority basis to Mary Scott
Losinksi wanted details on use of the ED at CGH. He asked the administrative resident